Permit: T14CM08580
Permit Details
Apply Date:
12/15/2014
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR DRHO3543 T14-M0052
Contractors:
- D R H TUCSON CONSTRUCTION
Permit Reviews
Permit Number - T14CM08580
Permit Status: Final
Permit Description: SFR DRHO3543 T14-M0052
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/15/2014 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 12/15/2014 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T14CM08580
Permit Status: Final
Permit Description: SFR DRHO3543 T14-M0052
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/15/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T14CM08580
Permit Description: SFR DRHO3543 T14-M0052
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/24/2015 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | |
| 11/24/2015 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | |
| 11/24/2015 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
| 11/30/2015 | ELECTRIC - TEMPORARY SERVICE | RCAMACHO | Approved | |
| 11/30/2015 | ELECTRIC - CABLE DROP | RCAMACHO | Approved | |
| 11/30/2015 | ELECTRIC - UFER | RCAMACHO | Approved | |
| 12/01/2015 | BUILDING PRE-SLAB | RCAMACHO | Approved | IVRS - Inspection :* |
| 12/01/2015 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | IVRS - Inspection :* |
| 12/10/2015 | ROOF NAILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 12/11/2015 | EXT METAL CLIPS/EXT SHEATHING | RCAMACHO | Approved | IVRS - Inspection :* |
| 12/28/2015 | MECHANICAL - INTERMEDIATE | BSTEVENS | Approved | IVRS - Inspection :* |
| 12/28/2015 | PLUMBING - GAS PRESSURE TEST | BSTEVENS | Approved | IVRS - Inspection :* |
| 12/28/2015 | PLUMBING - INTERMEDIATE | BSTEVENS | Approved | IVRS - Inspection :* |
| 12/28/2015 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | IVRS - Inspection :* |
| 12/28/2015 | U VALUE FOR WINDOW | BSTEVENS | Approved | IVRS - Inspection :* |
| 12/28/2015 | STUCCO MESH | BSTEVENS | Approved | IVRS - Inspection :* |
| 12/28/2015 | FRAMING | BSTEVENS | Approved | IVRS - Inspection :* |
| 01/05/2016 | SHEET ROCK NAILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 02/05/2016 | PLUMBING - GAS PRESS TEST FNL | RCAMACHO | Approved | IVRS - Inspection :* |
| 02/05/2016 | OUTDOOR LIGHTING FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 02/05/2016 | MECHANICAL - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 02/05/2016 | PLUMBING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 02/05/2016 | ELECTRIC - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 02/05/2016 | BUILDING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 02/08/2016 | GAS CLEARANCE | rcamacho | Approved |