Permit: T14CM08545
Permit Details
Apply Date:
12/12/2014
Applicant:
MIRAMONTE ARIZONA L L C *APA*
Description:
SFR MIRA197513 T13-M0041
Contractors:
- MIRAMONTE ARIZONA L L C *APA*
Permit Reviews
Permit Number - T14CM08545
Permit Status: C of o
Permit Description: SFR MIRA197513 T13-M0041
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/12/2014 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 12/12/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T14CM08545
Permit Status: C of o
Permit Description: SFR MIRA197513 T13-M0041
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/12/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T14CM08545
Permit Description: SFR MIRA197513 T13-M0041
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/17/2015 | PLUMBING - SEWER HCS CONNECT | BSTEVENS | Approved | |
| 04/17/2015 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | |
| 04/17/2015 | PLUMBING - YARD WTR LINE/TEST | BSTEVENS | Approved | |
| 04/28/2015 | ELECTRIC - UFER | BSTEVENS | Approved | |
| 04/28/2015 | BUILDING PRE-SLAB | BSTEVENS | Approved | |
| 04/28/2015 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | |
| 05/27/2015 | ROOF NAILING | BSTEVENS | Approved | |
| 05/27/2015 | EXT METAL CLIPS/EXT SHEATHING | BSTEVENS | Approved | |
| 05/27/2015 | ROOF NAILING | DQUINN | Approved | 4. ROOF NAILING MISSED AT: A) NEST TO ACCESS HOLE B) EAST FACE OF ENTRY PORCH C) 1/2 OF A ROW MISSED- 2 SHEETS NORTH OF SOUTHEAST SCUPPER |
| 05/27/2015 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | 1. 2ND FLOOR INTERIOR SHEARWALL NOT NAILED AT EAST END. 2. ALL KING STUDS IN A SHEARWALLS MUST BE NAILED, ESPECIALLY ABOVE HD'S 3. STRAP TOP PLATES TO PATIO DOOR HEADER |
| 06/08/2015 | TEP CLEARANCE - AM | DQUINN | Approved | ECO |
| 06/08/2015 | ELECTRIC - CABLE DROP | DQUINN | Approved | |
| 06/08/2015 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | |
| 06/26/2015 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
| 06/26/2015 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 06/26/2015 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | |
| 06/26/2015 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 06/26/2015 | U VALUE FOR WINDOW | DQUINN | Approved | |
| 06/26/2015 | STUCCO MESH | DQUINN | Approved | |
| 06/26/2015 | FRAMING | DQUINN | Approved | |
| 07/08/2015 | SHEET ROCK NAILING | DQUINN | Approved | |
| 09/16/2015 | PLUMBING - GAS PRESS TEST FNL | BSTEVENS | Approved | |
| 09/22/2015 | ELECTRIC - FINAL | DQUINN | Approved | |
| 09/22/2015 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
| 09/22/2015 | PLUMBING - FINAL | DQUINN | Approved | |
| 09/22/2015 | MECHANICAL - FINAL | DQUINN | Approved | |
| 09/24/2015 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |