Permit: T14CM08372
Permit Details
Status:
C of o
Type:
SINGLE FAMILY NEW
Address:
5007 N WILD LIFE DR
Address NEW:
5007 N WILD LIFE DR
Apply Date:
12/09/2014
Applicant:
MIRAMONTE ARIZONA L L C *APA*
Description:
SFR MIRA240213 T13-M0043
Contractors:
- MIRAMONTE ARIZONA L L C *APA*
Permit Reviews
Permit Number - T14CM08372
Permit Status: C of o
Permit Description: SFR MIRA240213 T13-M0043
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/09/2014 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 12/11/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T14CM08372
Permit Status: C of o
Permit Description: SFR MIRA240213 T13-M0043
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/09/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T14CM08372
Permit Description: SFR MIRA240213 T13-M0043
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/29/2015 | PLUMBING - SEWER HCS CONNECT | AQUIROZ | Approved | IVRS - Inspection :* |
| 06/29/2015 | PLUMBING - YARD WTR LINE/TEST | AQUIROZ | Approved | IVRS - Inspection :* |
| 06/29/2015 | PLUMBING - ROUGH, SOIL | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/02/2015 | ELECTRIC - UNDERGROUND | DQUINN | Approved | |
| 07/02/2015 | BUILDING PRE-SLAB | DQUINN | Approved | |
| 07/02/2015 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
| 08/04/2015 | ROOF NAILING | DQUINN | Approved | |
| 08/04/2015 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
| 09/09/2015 | U VALUE FOR WINDOW | DQUINN | Approved | |
| 09/09/2015 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | 13.75 LBS OF PRESSURE |
| 09/11/2015 | ELECTRIC - UFER | DQUINN | Approved | |
| 09/11/2015 | FRAMING | DQUINN | Approved | |
| 09/11/2015 | STUCCO MESH | DQUINN | Approved | |
| 09/11/2015 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
| 09/11/2015 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 09/11/2015 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 09/22/2015 | SHEET ROCK NAILING | MPUGH1 | Approved | IVRS - Inspection :* |
| 11/25/2015 | ELECTRIC - TEMPORARY SERVICE | MPUGH1 | Approved | IVRS - Inspection :* |
| 11/25/2015 | ELECTRIC - CABLE DROP | MPUGH1 | Approved | IVRS - Inspection :* |
| 11/27/2015 | TEP CLEARANCE - AM | MPUGH | Approved | TEC |
| 12/11/2015 | BUILDING - FINAL | BSTEVENS | Approved | |
| 12/11/2015 | ELECTRIC - FINAL | BSTEVENS | Approved | |
| 12/11/2015 | OUTDOOR LIGHTING FINAL | BSTEVENS | Approved | |
| 12/11/2015 | PLUMBING - GAS PRESS TEST FNL | BSTEVENS | Approved | |
| 12/11/2015 | PLUMBING - FINAL | BSTEVENS | Approved | |
| 12/11/2015 | MECHANICAL - FINAL | BSTEVENS | Approved | |
| 12/14/2015 | GAS CLEARANCE | bstevens | Approved |