Permit: T14CM08184
Permit Details
Status:
Final
Type:
COMMERCIAL ADDITION
Address:
2565 E COMMERCE CENTER PL
Address NEW:
2565 E COMMERCE CENTER PL
Apply Date:
12/02/2014
Applicant:
PAUL HOUGH / STEVE KELLEN
Description:
NEW UTILITY BUILDING AND FUEL CANOPY -RETAIL
Architects:
- DAVID RICHARD SCHUKAI
Contractors:
- SHAMES CONSTRUCTION COMPANY LTD
Permit Reviews
Permit Number - T14CM08184
Permit Status: Final
Permit Description: NEW UTILITY BUILDING AND FUEL CANOPY -RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/16/2015 | RESUBMITTAL | 02/13/2015 | COMPLETED |
| 02/13/2015 | RESUBMITTAL | 05/27/2015 | COMPLETED |
| 05/27/2015 | RESUBMITTAL | 06/02/2015 | COMPLETED |
| 06/02/2015 | RESUBMITTAL | 06/23/2015 | COMPLETED |
| 10/23/2015 | REVISION - - 1ST | 10/26/2015 | COMPLETED |
| 11/06/2014 | COMMERCIAL - NEW | 01/16/2015 | COMPLETED |
| 12/01/2015 | REVISION - - 2ND | 12/02/2015 | COMPLETED |
| 12/23/2015 | REVISION - - 3RD | 01/30/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T14CM08184
Permit Status: Final
Permit Description: NEW UTILITY BUILDING AND FUEL CANOPY -RETAIL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/02/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T14CM08184
Permit Description: NEW UTILITY BUILDING AND FUEL CANOPY -RETAIL
Total Completed Inspections - 33
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/31/2015 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | IVRS - Inspection :* |
| 07/31/2015 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | IVRS - Inspection :* |
| 08/17/2015 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | CMU WALLS TOPPED-OUT - OK TO GROUT |
| 08/17/2015 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* |
| 10/16/2015 | ELECTRIC - UNDERGROUND | MRAMBER | Approved | IVRS - Inspection :* |
| 10/28/2015 | ELECTRIC - UFER | MRAMBER | Approved | IVRS - Inspection :* |
| 11/17/2015 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 11/17/2015 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 11/17/2015 | FRAMING | MRAMBER | Approved | IVRS - Inspection :* |
| 11/18/2015 | ELECTRIC - SERVICE UPGRADE | MRAMBER | Approved | IVRS - Inspection :* |
| 11/19/2015 | TEP CLEARANCE - AM | MRAMBER | Approved | INCR |
| 12/04/2015 | ELECTRIC - FINAL | MRAMBER | Approved | DISC MAIN OK, OK TO ENERGIZE |
| 01/05/2016 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 01/07/2016 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 01/07/2016 | PLUMBING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 01/07/2016 | PLUMBING - SEWER HCS CONNECT | MRAMBER | Approved | IVRS - Inspection :* |
| 01/07/2016 | PLUMBING - YARD WTR LINE/TEST | MRAMBER | Approved | IVRS - Inspection :* |
| 01/07/2016 | PLUMBING - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 01/07/2016 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 01/07/2016 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 01/07/2016 | BUILDING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 01/07/2016 | U VALUE FOR WINDOW | MRAMBER | Approved | IVRS - Inspection :* |
| 01/07/2016 | BUILDING PRE-SLAB | MRAMBER | Approved | IVRS - Inspection :* |
| 01/08/2016 | FIRE - FINAL | jhinric1 | Approved | E-stop working. Warning placards in place. Hoses secure and proper length. Extinguishers present. Shear valves secure. Dispenser detectors present and proper length. |
| 01/08/2016 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 01/08/2016 | PLUMBING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 01/08/2016 | PLUMBING - ROOF DRAINS | MRAMBER | Approved | IVRS - Inspection :* |
| 01/12/2016 | NPPO - FINAL | DROBERTS | Approved | |
| 01/12/2016 | SIGN - FINAL | DROBERTS | Approved | |
| 02/24/2016 | LANDSCAPE - FINAL | DROBERTS | Approved | |
| 02/24/2016 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 02/25/2016 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 02/26/2016 | RIGHT OF WAY - FINAL | DRUSSELL | Approved |