Permit Details

Status:
L of c
Type:
COMMERCIAL ALTERATION
Apply Date:
10/28/2014
Applicant:
ELISA MORROW
Description:
T.I;OFFICE RESTROOMS 1ST FLOOR COM AREA
Architects:
  • SWAN WAYNE E
Contractors:
  • G AND J DEVELOPMENT INC ,

Permit Reviews

Permit Number - T14CM07270
Permit Status: L of c
Permit Description: T.I;OFFICE RESTROOMS 1ST FLOOR COM AREA
Start Date Submittal Complete Date Status  
10/28/2014 COMMERCIAL - TI 11/04/2014 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T14CM07270
Permit Status: L of c
Permit Description: T.I;OFFICE RESTROOMS 1ST FLOOR COM AREA
Total Outstanding Activity Conditions - 1
Date Name
10/28/2014 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: L of c
Permit Number: T14CM07270
Permit Description: T.I;OFFICE RESTROOMS 1ST FLOOR COM AREA
Total Completed Inspections - 15
Date Description Inspector Results Comments
11/28/2014 PLUMBING - ROUGH, SOIL BBENEDOI Approved IVRS - Inspection :*
12/05/2014 PLUMBING - INTERMEDIATE BBENEDON Approved DEMO OK (OK TO COVER). INSTALL PLUGS IN YOUR OPEN DWV. YOU MAY BE REQUIRED TO PAY RE-INSPECTION FEES IF YOU FAIL TO COMPLY
12/05/2014 PLUMBING - INTERMEDIATE BBENEDOI Approved IVRS - Inspection :*
12/05/2014 PLUMBING - PROGRESS BBENEDOI Approved IVRS - Inspection :
See detailed listing on site.| 999*
12/09/2014 FIRE - FINAL CBASALDUA Approved
01/12/2015 ELECTRIC - INTERMEDIATE BBENEDOI Approved IVRS - Inspection :*
01/12/2015 FRAMING BBENEDOI Approved IVRS - Inspection :*
01/20/2015 PLUMBING - ABOVE CEILING BBENEDOI Approved IVRS - Inspection :*
01/20/2015 SHEET ROCK NAILING BBENEDOI Approved IVRS - Inspection :*
03/19/2015 ELECTRIC - FINAL BBENEDOI Approved IVRS - Inspection :*
03/19/2015 BUILDING ABOVE CEILING BBENEDOI Approved IVRS - Inspection :*
03/19/2015 FIRE SPKLR - FINAL CSCHULTZ Approved
03/20/2015 PLUMBING - FINAL BBENEDON Approved ADJUST URINAL
03/20/2015 PLUMBING - FINAL BBENEDOI Approved IVRS - Inspection :*
03/20/2015 BUILDING - FINAL BBENEDOI Approved IVRS - Inspection :*

Documents

File Name Document Type  
None LETTER OF COMPLETION VIEW
001_G-1.TIF CONSTRPLANS VIEW
002_A-1.TIF CONSTRPLANS VIEW
003_A-2.TIF CONSTRPLANS VIEW
004_A-3.TIF CONSTRPLANS VIEW
005_P-1.TIF CONSTRPLANS VIEW
006_P-2.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW