Permit: T14CM06758
Permit Details
Apply Date:
10/08/2014
Applicant:
N/A
Description:
NEW SFR TD#16-88-42 T07-M0004
Contractors:
- MEAD MEYER CONSTRUCTION INC
Permit Reviews
Permit Number - T14CM06758
Permit Status: Final
Permit Description: NEW SFR TD#16-88-42 T07-M0004
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/08/2014 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 10/09/2014 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T14CM06758
Permit Status: Final
Permit Description: NEW SFR TD#16-88-42 T07-M0004
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/08/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T14CM06758
Permit Description: NEW SFR TD#16-88-42 T07-M0004
Total Completed Inspections - 30
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/29/2014 | PLUMBING - SEWER HCS CONNECT | WLAHR | Approved | 4" SDR AT NORTH SIDE OF PROPERTY TESTED OK |
| 10/29/2014 | PLUMBING - SEWER HCS CONNECT | WLAHR | Approved | IVRS - Inspection :* |
| 11/24/2014 | PLUMBING - PROGRESS | MRAMBER | Approved | 1. PLUM ROUGH OK TO COVER, PLUM ROUGH NOT ON PERMIT CARD |
| 11/24/2014 | PLUMBING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 12/16/2014 | ELECTRIC - UFER | MRAMBER | Approved | IVRS - Inspection :* |
| 12/16/2014 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | IVRS - Inspection :* |
| 12/16/2014 | BUILDING PRE-SLAB | MRAMBER | Approved | IVRS - Inspection :* |
| 03/20/2015 | ROOF NAILING | MRAMBER | Approved | IVRS - Inspection :* |
| 04/02/2015 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | 1. PROVIDE WET LOCATION LIGHTING AT SHOWERS 2. SHOWER PAN REQUIRED |
| 04/02/2015 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 04/02/2015 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 04/02/2015 | FRAMING | MRAMBER | Approved | IVRS - Inspection :* |
| 04/14/2015 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 04/20/2015 | STUCCO MESH | MRAMBER | Approved | IVRS - Inspection :* |
| 04/23/2015 | PLUMBING - YARD WTR LINE/TEST | MRAMBER | Approved | IVRS - Inspection :* |
| 05/07/2015 | SHEET ROCK NAILING | MRAMBER | Approved | IVRS - Inspection :* |
| 06/09/2015 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | IVRS - Inspection :* |
| 06/10/2015 | TEP CLEARANCE - AM | DSANTACRUZ | Approved | TEC |
| 02/25/2016 | STEM WALL/RETAINING WALL | BSTEVENS | Approved | |
| 02/25/2016 | BUILDING - PROGRESS | BSTEVENS | Approved | |
| 02/25/2016 | ELECTRIC - UNDERGROUND | BSTEVENS | Approved | |
| 02/25/2016 | ELECTRIC - CABLE DROP | BSTEVENS | Approved | |
| 02/25/2016 | ELECTRIC - PROGRESS | BSTEVENS | Approved | |
| 02/25/2016 | ELECTRIC - FINAL | BSTEVENS | Approved | |
| 02/25/2016 | PLUMBING - PRE SLAB | BSTEVENS | Approved | |
| 02/25/2016 | PLUMBING - FINAL | BSTEVENS | Approved | |
| 02/25/2016 | MECHANICAL - PROGRESS | BSTEVENS | Approved | |
| 02/25/2016 | MECHANICAL - FINAL | BSTEVENS | Approved | |
| 03/09/2016 | PLUMBING - GAS PRESS TEST FNL | bstevens | Approved | |
| 03/09/2016 | BUILDING - FINAL | BSTEVENS | Approved |