Permit: T14CM06035
Permit Details
Apply Date:
09/12/2014
Applicant:
CAYLOR CONSTRUCTION COMPANY , RO
Description:
T.I;OFFICE
Contractors:
- CAYLOR CONSTRUCTION COMPANY , RO
Permit Reviews
Permit Number - T14CM06035
Permit Status: C of o
Permit Description: T.I;OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/12/2014 | COMMERCIAL - TI | 09/12/2014 | COMPLETED |
10/10/2014 | REVISION - - 1ST | 10/10/2014 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T14CM06035
Permit Status: C of o
Permit Description: T.I;OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/12/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T14CM06035
Permit Description: T.I;OFFICE
Total Completed Inspections - 17
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/07/2014 | FRAMING | MPUGH | Approved | IVRS - Inspection :* |
10/09/2014 | ELECTRIC - INTERMEDIATE | MPUGH | Approved | IVRS - Inspection :* |
10/15/2014 | PLUMBING - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
10/15/2014 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
11/10/2014 | MECHANICAL - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
11/10/2014 | PLUMBING - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
11/10/2014 | ELECTRIC - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
11/10/2014 | BUILDING ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
12/08/2014 | FIRE - FINAL | CSCHULTZ | Approved | Need the following annual inspection reports completed before C of O will be issued: 1. Fire Sprinkler inspection 2. Fire Pump test inspection 3. Fire alarm test inspection 4. Stairwell pressurization test done 5. Emergency generator full load test done 6. Fire doors test done |
12/08/2014 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | Need the following annual inspection reports completed before C of O will be issued: 1. Fire Sprinkler inspection 2. Fire Pump test inspection 3. Fire alarm test inspection 4. Stairwell pressurization test done 5. Emergency generator full load test done 6. Fire doors test done |
12/08/2014 | MECHANICAL - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
12/08/2014 | PLUMBING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
12/08/2014 | ELECTRIC - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
12/08/2014 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
12/09/2014 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
12/15/2014 | MECHANICAL - INTERMEDIATE | BSTEVENS | Approved | IVRS - Inspection :* |
12/15/2014 | PLUMBING - FINAL | BSTEVENS | Approved | IVRS - Inspection :* |