Permit: T14CM05446
Permit Details
Apply Date:
08/20/2014
Applicant:
STERTZ CONSTRUCTION LLC
Description:
LAUNDRY BUILDING
Contractors:
- STERTZ CONSTRUCTION LLC
Permit Reviews
Permit Number - T14CM05446
Permit Status: Final
Permit Description: LAUNDRY BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/20/2014 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/28/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T14CM05446
Permit Status: Final
Permit Description: LAUNDRY BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/20/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T14CM05446
Permit Description: LAUNDRY BUILDING
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/29/2014 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
| 08/29/2014 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | |
| 08/29/2014 | ELECTRIC - UNDERGROUND | DQUINN | Approved | UFER IS OK |
| 08/29/2014 | BUILDING PRE-SLAB | DQUINN | Approved | |
| 08/29/2014 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
| 09/10/2014 | FRAMING | DQUINN | Approved | |
| 09/10/2014 | ROOF NAILING | DQUINN | Approved | |
| 09/10/2014 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
| 09/12/2014 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 09/12/2014 | PLUMBING - PROGRESS | DQUINN | Approved | |
| 09/12/2014 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 09/12/2014 | ELECTRIC - PROGRESS | DQUINN | Approved | |
| 09/12/2014 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
| 09/12/2014 | SHEET ROCK NAILING | DQUINN | Approved | |
| 09/17/2014 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/17/2014 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/24/2014 | TEP CLEARANCE - AM | DQUINN | Approved | INC UNDERGROUND FROM NEW PANEL @ LAUNDRY TO EAST BLDG OK TO BACKFILL |
| 09/24/2014 | ELECTRIC - SERVICE UPGRADE | DQUINN | Approved | |
| 10/02/2014 | MECHANICAL - FINAL | DQUINN | Approved | |
| 10/02/2014 | PLUMBING - FINAL | DQUINN | Approved | |
| 10/02/2014 | ELECTRIC - FINAL | DQUINN | Approved | |
| 10/02/2014 | BUILDING - PROGRESS | DQUINN | Approved | |
| 10/02/2014 | FIRE - FINAL | CBASALDUA | Approved | |
| 10/15/2014 | BUILDING - FINAL | BSTEVENS | Approved |