Permit: T14CM04928
Permit Details
Apply Date:
08/01/2014
Applicant:
VENEZIANO, PHILIP JOHN
Description:
NEW METAL BUILDING
Architects:
- VENEZIANO, PHILIP JOHN
Contractors:
- COBRE BUILDING SYSTEMS INC ,
Permit Reviews
Permit Number - T14CM04928
Permit Status: C of o
Permit Description: NEW METAL BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/27/2015 | REVISION - - 1ST | 02/27/2015 | COMPLETED |
| 02/27/2015 | REVISION - - 1ST | 09/16/2015 | COMPLETED |
| 08/01/2014 | PLANS OK TO SUBMIT - COMM | 08/01/2014 | COMPLETED |
| 08/01/2014 | COMMERCIAL - NEW | 08/26/2014 | COMPLETED |
| 09/05/2014 | RESUBMITTAL | 09/17/2014 | COMPLETED |
| 09/17/2014 | RESUBMITTAL | 09/17/2014 | COMPLETED |
| 09/17/2014 | OTHER | 11/03/2014 | COMPLETED |
| 09/18/2015 | REVISION - - 1ST | 09/18/2015 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T14CM04928
Permit Status: C of o
Permit Description: NEW METAL BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/01/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T14CM04928
Permit Description: NEW METAL BUILDING
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/19/2015 | BUILDING PRE-SLAB | MRAMBER | Approved | IVRS - Inspection :* |
| 05/28/2015 | PLUMBING - GAS PRESSURE TEST | MRAMBER | Approved | IVRS - Inspection :* |
| 05/28/2015 | EXT METAL CLIPS/EXT SHEATHING | MRAMBER | Approved | IVRS - Inspection :* |
| 06/25/2015 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | PER MECH FINAL |
| 06/25/2015 | PLUMBING - YARD WTR LINE/TEST | MRAMBER | Approved | PER PL FINAL |
| 06/25/2015 | ELECTRIC - OUTDOOR LIGHTING | MRAMBER | Approved | PER EL FINAL |
| 06/25/2015 | STEM WALL/RETAINING WALL | MRAMBER | Approved | PER BU FINAL |
| 06/25/2015 | PLUMBING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 06/25/2015 | ELECTRIC - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 06/25/2015 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 06/25/2015 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 06/25/2015 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | IVRS - Inspection :* |
| 06/25/2015 | FIRE - FINAL | CBASALDUA | Approved | |
| 06/25/2015 | PLUMBING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 06/25/2015 | BUILDING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 06/25/2015 | FIREWALL/FIREBARRIER/FIRESTOP | MRAMBER | Approved | IVRS - Inspection :* |
| 06/26/2015 | RIGHT OF WAY - FINAL | CM | Approved | |
| 06/26/2015 | NPPO - FINAL | RLEDONNE | Approved | |
| 06/26/2015 | SIGN - FINAL | RLEDONNE | Approved | |
| 06/26/2015 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 06/26/2015 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 09/14/2015 | ELECTRIC - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 09/14/2015 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 09/14/2015 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 09/15/2015 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved |