Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Address NEW:
914 E SPEEDWAY BL #110
Apply Date:
07/15/2014
Applicant:
ROBERT WILSEY
Description:
RESTAURANT
Contractors:
  • GALAXY BUILDERS L L C

Permit Reviews

Permit Number - T14CM04397
Permit Status: C of o
Permit Description: RESTAURANT
Start Date Submittal Complete Date Status  
07/15/2014 COMMERCIAL - TI 07/15/2014 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T14CM04397
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
Date Name
07/15/2014 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T14CM04397
Permit Description: RESTAURANT
Total Completed Inspections - 25
Date Description Inspector Results Comments
08/11/2014 PLUMBING - ROUGH, SOIL BSTEVENS Approved
08/12/2014 BUILDING PRE-SLAB BSTEVENS Approved INFILL AT PLUMBING POUR BACKS OK TO POUR
08/19/2014 FRAMING BSTEVENS Approved
08/19/2014 PLUMBING - INTERMEDIATE BSTEVENS Approved
08/19/2014 PLUMBING - PROGRESS BSTEVENS Approved
08/19/2014 ELECTRIC - INTERMEDIATE BSTEVENS Approved
08/22/2014 MECHANICAL - ABOVE CEILING BSTEVENS Approved OK TO CLOSE CEILINGS
08/22/2014 ELECTRIC - ABOVE CEILING BSTEVENS Approved
08/25/2014 SHEET ROCK NAILING BSTEVENS Approved
09/16/2014 PLUMBING - ABOVE CEILING BSTEVENS Approved
09/16/2014 PLUMBING - GAS PRESSURE TEST BSTEVENS Approved
09/16/2014 MECHANICAL - HOODS BSTEVENS Approved
09/17/2014 GAS CLEARANCE BSTEVENS Approved
09/19/2014 HEALTH DEPT - FINAL 724-7908 NRAMIREZ Approved
09/19/2014 FIRE - KITCHEN EXH HOOD FINAL CBASALDUA Approved
09/19/2014 FIRE - FINAL CBASALDUA Approved
09/19/2014 BUILDING - FINAL BSTEVENS Approved
09/19/2014 PLUMBING - FINAL BSTEVENS Approved
09/19/2014 MECHANICAL - INTERMEDIATE BSTEVENS Approved
09/19/2014 MECHANICAL - FINAL BSTEVENS Approved
09/19/2014 ELECTRIC - UNDERGROUND BSTEVENS Approved
09/19/2014 ELECTRIC - PROGRESS BSTEVENS Approved
09/19/2014 ELECTRIC - FINAL BSTEVENS Approved
09/19/2014 BUILDING - PROGRESS BSTEVENS Approved
09/19/2014 BUILDING ABOVE CEILING BSTEVENS Approved