Permit: T14CM04141
Permit Details
Status:
Final
Type:
SINGLE FAMILY ADDITION
Address:
4049 E CAMINO DE LA COLINA
Address NEW:
4049 E CAMINO DE LA COLINA
Apply Date:
07/02/2014
Applicant:
RYAN KIPPES
Description:
ADD TWO BEDROOMS, BATHROOM AND LAUNDRY ROOM TO RES
Permit Reviews
Permit Number - T14CM04141
Permit Status: Final
Permit Description: ADD TWO BEDROOMS, BATHROOM AND LAUNDRY ROOM TO RES
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/02/2014 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 08/20/2014 | COMPLETED |
| 08/20/2014 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 10/08/2014 | COMPLETED |
| 10/09/2014 | RESUBMITTAL | 10/13/2014 | COMPLETED |
| 10/13/2014 | RESUBMITTAL | 10/17/2014 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T14CM04141
Permit Status: Final
Permit Description: ADD TWO BEDROOMS, BATHROOM AND LAUNDRY ROOM TO RES
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/02/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T14CM04141
Permit Description: ADD TWO BEDROOMS, BATHROOM AND LAUNDRY ROOM TO RES
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/10/2014 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | IVRS - Inspection :* |
| 11/19/2014 | BUILDING PRE-SLAB | RMORENO | Approved | IVRS - Inspection :* |
| 11/19/2014 | STEM WALL/RETAINING WALL | RMORENO | Approved | IVRS - Inspection :* |
| 11/25/2014 | PLUMBING - GAS PRESSURE TEST | RMORENO | Approved | IVRS - Inspection :* |
| 11/26/2014 | GAS CLEARANCE | RMORENO | Approved | |
| 03/25/2015 | TEP CLEARANCE - AM | RMORENO | Approved | INCR |
| 03/26/2015 | ROOF NAILING | RMORENO | Approved | IVRS - Inspection :* |
| 03/26/2015 | EXT METAL CLIPS/EXT SHEATHING | RMORENO | Approved | IVRS - Inspection :* |
| 05/22/2015 | U VALUE FOR WINDOW | BBENEDOI | Approved | IVRS - Inspection :* |
| 05/22/2015 | STUCCO MESH | BBENEDOI | Approved | IVRS - Inspection :* |
| 05/29/2015 | MECHANICAL - INTERMEDIATE | BBENEDOI | Approved | IVRS - Inspection :* |
| 05/29/2015 | ELECTRIC - INTERMEDIATE | BBENEDOI | Approved | IVRS - Inspection :* |
| 05/29/2015 | FRAMING | BBENEDOI | Approved | IVRS - Inspection :* |
| 10/14/2015 | PLUMBING - INTERMEDIATE | BBENEDOI | Approved | IVRS - Inspection :* |
| 10/14/2015 | PLUMBING - ROUGH, SOIL | BBENEDOI | Approved | IVRS - Inspection :* |
| 01/20/2016 | MECHANICAL - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 01/20/2016 | PLUMBING - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 01/20/2016 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 01/20/2016 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 01/20/2016 | BUILDING - FINAL | RMORENO | Approved | IVRS - Inspection :* |