Permit: T14CM03857
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
5850 N 1ST AV BLDG #2
Address NEW:
5850 N 1ST AV BLDG #2
Apply Date:
06/20/2014
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
MAINTENANCE SHOP
Architects:
- MICKELBERG, PAUL DAVID
Contractors:
- KITTLE DESIGN AND CONSTRUCTION L L C
Outstanding Activity Conditions
Permit Number - T14CM03857
Permit Status: C of o
Permit Description: MAINTENANCE SHOP
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/20/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T14CM03857
Permit Description: MAINTENANCE SHOP
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/29/2015 | PLUMBING - ROUGH, SOIL | BBENEDOI | Approved | IVRS - Inspection :* |
| 05/04/2015 | EXCAVATION/LAYOUT REBAR & ZON | BBENEDOI | Approved | IVRS - Inspection :* |
| 05/19/2015 | REINFORCED MASONRY PRE-GROUT | BSTEVENS | Approved | |
| 06/09/2015 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | |
| 06/25/2015 | FRAMING | BBENEDOI | Approved | IVRS - Inspection :* |
| 08/06/2015 | ELECTRIC - PROGRESS | BBENEDOI | Approved | IVRS - Inspection :* |
| 08/20/2015 | MECHANICAL - FINAL | BBENEDOI | Approved | IVRS - Inspection :* |
| 08/20/2015 | PLUMBING - GAS PRESSURE TEST | BBENEDOI | Approved | IVRS - Inspection :* |
| 08/20/2015 | FIRE - FINAL | CBASALDUA | Approved | |
| 09/14/2015 | ELECTRIC - FINAL | BBENEDOI | Approved | IVRS - Inspection :* |
| 09/14/2015 | BUILDING - PROGRESS | BBENEDOI | Approved | IVRS - Inspection :* |
| 09/18/2015 | PLUMBING - INTERMEDIATE | bbenedon | Approved | |
| 09/18/2015 | STEM WALL/RETAINING WALL | bbenedon | Approved | |
| 09/18/2015 | U VALUE FOR WINDOW | BBENEDOI | Approved | IVRS - Inspection :* |
| 09/18/2015 | MECHANICAL - HOOD SYSTEMS | BBENEDOI | Approved | IVRS - Inspection :* |
| 09/18/2015 | MECHANICAL - INTERMEDIATE | BBENEDOI | Approved | IVRS - Inspection :* |
| 09/18/2015 | SHEET ROCK NAILING | BBENEDOI | Approved | IVRS - Inspection :* |
| 09/18/2015 | BUILDING ABOVE CEILING | BBENEDOI | Approved | IVRS - Inspection :* |
| 09/18/2015 | ROOF NAILING | BBENEDOI | Approved | IVRS - Inspection :* |
| 09/18/2015 | BUILDING PRE-SLAB | BBENEDOI | Approved | IVRS - Inspection :* |
| 09/18/2015 | ELECTRIC - ABOVE CEILING | BBENEDOI | Approved | IVRS - Inspection :* |
| 09/18/2015 | PLUMBING - PROGRESS | BBENEDOI | Approved | IVRS - Inspection :* |
| 09/18/2015 | PLUMBING - FINAL | BBENEDOI | Approved | IVRS - Inspection :* |
| 09/18/2015 | BUILDING - FINAL | BBENEDOI | Approved | IVRS - Inspection :* |