Permit: T14CM03704
Permit Details
Apply Date:
06/17/2014
Applicant:
N/A
Description:
ADD NEW 293 S.F. LAUNDRY FACILITY
Architects:
- MEYER WILLIAM (CHUCK)
Contractors:
- HAYES CONSTRUCTION INC , THOMAS
Permit Reviews
Permit Number - T14CM03704
Permit Status: Final
Permit Description: ADD NEW 293 S.F. LAUNDRY FACILITY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/17/2014 | COMMERCIAL - TI | 06/27/2014 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T14CM03704
Permit Status: Final
Permit Description: ADD NEW 293 S.F. LAUNDRY FACILITY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/17/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T14CM03704
Permit Description: ADD NEW 293 S.F. LAUNDRY FACILITY
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/04/2014 | PLUMBING - ROUGH, SOIL | MPUGH | Approved | IVRS - Inspection :* |
| 12/11/2014 | BUILDING PRE-SLAB | DQUINN | Approved | |
| 12/11/2014 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
| 12/23/2014 | ROOF NAILING | DQUINN | Approved | |
| 12/23/2014 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
| 01/16/2015 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 01/16/2015 | SITE - SEWER | DQUINN | Approved | |
| 01/16/2015 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | |
| 01/16/2015 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 01/16/2015 | ELECTRIC - SERVICE UPGRADE | DQUINN | Approved | |
| 01/16/2015 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
| 01/16/2015 | STUCCO MESH | DQUINN | Approved | |
| 01/16/2015 | FRAMING | DQUINN | Approved | |
| 01/21/2015 | SHEET ROCK NAILING | DQUINN | Approved | |
| 03/03/2015 | FIRE - FINAL | nsprenger | Approved | |
| 03/04/2015 | MECHANICAL - FINAL | DQUINN | Approved | |
| 03/04/2015 | PLUMBING - PROGRESS | DQUINN | Approved | PER PLMB FINAL |
| 03/04/2015 | PLUMBING - FINAL | DQUINN | Approved | |
| 03/04/2015 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | PER ELEC FINAL |
| 03/04/2015 | ELECTRIC - FINAL | DQUINN | Approved | |
| 03/04/2015 | BUILDING - PROGRESS | DQUINN | Approved | PER BLDG FINAL |
| 03/04/2015 | BUILDING ABOVE CEILING | DQUINN | Approved | PER BLDG FINAL |
| 03/04/2015 | BUILDING - FINAL | DQUINN | Approved |