Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Address NEW:
6296 E GRANT RD #110
Apply Date:
04/04/2014
Applicant:
N/A
Description:
OFFICE
Architects:
  • GARCIA DAVID V
Contractors:
  • DIVISION II CONSTRUCTION COMPANY

Permit Reviews

Permit Number - T14CM01893
Permit Status: C of o
Permit Description: OFFICE
Start Date Submittal Complete Date Status  
04/04/2014 COMMERCIAL - TI 04/09/2014 COMPLETED Review Details
04/09/2014 COMMERCIAL - TI 04/10/2014 COMPLETED Review Details
04/10/2014 OTHER 04/14/2014 COMPLETED Review Details
05/23/2014 REVISION - WALK THRU 05/23/2014 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T14CM01893
Permit Status: C of o
Permit Description: OFFICE
Total Outstanding Activity Conditions - 1
Date Name
04/04/2014 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T14CM01893
Permit Description: OFFICE
Total Completed Inspections - 34
Date Description Inspector Results Comments
05/15/2014 EXCAVATION/LAYOUT REBAR & ZON BSTEVENS Approved IVRS - Inspection :*
05/19/2014 FRAMING BSTEVENS Approved
05/21/2014 REINFORCED MASONRY PRE-GROUT BSTEVENS Approved IVRS - Inspection :*
05/21/2014 STEM WALL/RETAINING WALL BSTEVENS Approved IVRS - Inspection :*
05/21/2014 ELECTRIC - UFER BSTEVENS Approved IVRS - Inspection :*
05/27/2014 ELECTRIC - UNDERGROUND BSTEVEN Approved
05/29/2014 SHEET ROCK NAILING BSTEVENS Approved
05/29/2014 PLUMBING - INTERMEDIATE BSTEVENS Approved
06/24/2014 TEP CLEARANCE - AM JMILITEL Approved ECO 150, 130, OWNERS PANEL
07/02/2014 ELECTRIC - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
07/03/2014 ELECTRIC - PROGRESS JMILITEL Approved IVRS - Inspection :*
07/03/2014 BUILDING ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
07/03/2014 ELECTRIC - TEMP POWER FOR TEST JMILITEL Approved IVRS - Inspection :*
07/03/2014 PLUMBING - PRE SLAB JMILITEL Approved IVRS - Inspection :*
07/03/2014 PLUMBING - ROUGH, SOIL JMILITEL Approved IVRS - Inspection :*
07/03/2014 ELECTRIC - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
07/03/2014 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
07/03/2014 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
07/03/2014 PLUMBING - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
07/11/2014 RIGHT OF WAY - FINAL TWOLFGAN Approved
07/11/2014 PLUMBING - PROGRESS JMILITEL Approved IVRS - Inspection :*
07/11/2014 BUILDING - PROGRESS JMILITEL Approved IVRS - Inspection :*
07/14/2014 NPPO - FINAL RLEDONNE Approved
07/14/2014 SIGN - FINAL RLEDONNE Approved
07/14/2014 LANDSCAPE - FINAL RLEDONNE Approved
07/15/2014 FIRE SPKLR - FINAL CBASALDU Approved
07/15/2014 FIRE SPKLR - FINAL CBASALDU Approved 1. Subcontractor permit needs to be finaled.
08/19/2014 FIRE - ALARM FINAL wmotto1 Approved
08/19/2014 FIRE - FINAL wmotto1 Approved
08/20/2014 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
08/20/2014 PLUMBING - FINAL JMILITEL Approved IVRS - Inspection :*
08/20/2014 ELECTRIC - FINAL JMILITEL Approved IVRS - Inspection :*
08/20/2014 BUILDING - FINAL JMILITEL Approved IVRS - Inspection :*
08/20/2014 ENGINEERING - FINAL RLEDONNE Approved