Permit: T14CM01365
Permit Details
Apply Date:
03/10/2014
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW COMMERCIAL BUILDING- COMMUNITY CENTER
Architects:
- EGLIN, EVAN SAR
Contractors:
- TOFEL CONSTRUCTION
Permit Reviews
Permit Number - T14CM01365
Permit Status: C of o
Permit Description: NEW COMMERCIAL BUILDING- COMMUNITY CENTER
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/10/2014 | PLANS OK TO SUBMIT - COMM | 06/02/2014 | COMPLETED |
06/02/2014 | COMMERCIAL - NEW | 07/23/2014 | COMPLETED |
07/23/2014 | RESUBMITTAL - TI ALL | 08/12/2014 | COMPLETED |
08/12/2014 | RESUBMITTAL | 09/12/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T14CM01365
Permit Status: C of o
Permit Description: NEW COMMERCIAL BUILDING- COMMUNITY CENTER
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/10/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T14CM01365
Permit Description: NEW COMMERCIAL BUILDING- COMMUNITY CENTER
Total Completed Inspections - 36
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/24/2014 | ELECTRIC - UNDERGROUND | MPUGH | Approved | CONDUIT OK AT UNIT E |
10/24/2014 | ELECTRIC - UNDERGROUND | MPUGH | Approved | IVRS - Inspection :* |
10/30/2014 | SITE - SEWER | MPUGH | Approved | IVRS - Inspection :* |
10/31/2014 | PLUMBING - ROUGH, SOIL | MPUGH | Approved | IVRS - Inspection :* |
10/31/2014 | PLUMBING - PROGRESS | MPUGH | Approved | IVRS - Inspection :* |
10/31/2014 | PLUMBING - YARD WTR LINE/TEST | MPUGH | Approved | IVRS - Inspection :* |
11/06/2014 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
11/06/2014 | ELECTRIC - UFER | DQUINN | Approved | |
11/06/2014 | ELECTRIC - TEMP POWER FOR TEST | DQUINN | Approved | |
11/07/2014 | TEP CLEARANCE - AM | DQUINN | Approved | TMPP |
11/19/2014 | EXT METAL CLIPS/EXT SHEATHING | BSTEVENS | Approved | IVRS - Inspection :* |
11/19/2014 | ROOF NAILING | BSTEVENS | Approved | IVRS - Inspection :* |
11/21/2014 | BUILDING - PROGRESS | MPUGH | Approved | OK TO COVER SUFFIT FOR DRY WALL STOP |
11/21/2014 | BUILDING - PROGRESS | MPUGH | Approved | IVRS - Inspection :* |
02/11/2015 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection :* |
07/21/2015 | RIGHT OF WAY - FINAL | JCASTRO | Approved | |
07/27/2015 | FIRE - FINAL | CSCHULTZ | Approved | |
07/29/2015 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
07/29/2015 | ELECTRIC - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
07/29/2015 | PLUMBING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
07/29/2015 | MECHANICAL - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
07/29/2015 | MECHANICAL - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
07/29/2015 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
07/29/2015 | ELECTRIC - OUTDOOR LIGHTING | AQUIROZ | Approved | IVRS - Inspection :* |
07/29/2015 | ELECTRIC - ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
07/29/2015 | PLUMBING - ROOF DRAINS | AQUIROZ | Approved | IVRS - Inspection :* |
07/29/2015 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
07/29/2015 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
07/29/2015 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
07/29/2015 | ELECTRIC - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
07/30/2015 | NPPO - FINAL | RLEDONNE | Approved | |
07/30/2015 | SIGN - FINAL | RLEDONNE | Approved | |
07/30/2015 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
08/26/2015 | PLUMBING - INTERMEDIATE | AQUIROZ | Approved | PER PLMB FINAL |
08/26/2015 | FRAMING | AQUIROZ | Approved | PER BLDG FINAL |
09/09/2015 | ENGINEERING - FINAL | MRUSSO | Approved | PER PHONE CONVERSATION |