Permit: T13CM07337
Permit Details
Apply Date:
12/05/2013
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW SELF STORAGE BUILDING
Architects:
- JW ADRAGNA COMPANY
Contractors:
- SIERRA LAND SURVEYING AND DEVELO
Permit Reviews
Permit Number - T13CM07337
Permit Status: C of o
Permit Description: NEW SELF STORAGE BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/08/2014 | RESUBMITTAL | 01/10/2014 | COMPLETED |
12/05/2013 | PLANS OK TO SUBMIT - COMM | 12/05/2013 | COMPLETED |
12/05/2013 | COMMERCIAL - NEW | 12/19/2013 | COMPLETED |
12/19/2013 | RESUBMITTAL | 01/08/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM07337
Permit Status: C of o
Permit Description: NEW SELF STORAGE BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/05/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM07337
Permit Description: NEW SELF STORAGE BUILDING
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/17/2014 | EXCAVATION/LAYOUT REBAR & ZON | BBENEDON | Approved | IVRS - Inspection :* |
01/23/2014 | BUILDING PRE-SLAB | BBENEDON | Approved | IVRS - Inspection :* |
06/19/2014 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
07/17/2014 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
07/17/2014 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
07/17/2014 | ELECTRIC - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
07/17/2014 | MECHANICAL - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
08/11/2014 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* OK TO COVER |
08/11/2014 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
09/17/2014 | ELECTRIC - UNDERGROUND | BSTEVENS | Approved | IVRS - Inspection :* |
12/31/2014 | FRAMING | BBENEDON | Approved | SEE DETAILS ON PAGE S-13 |
12/31/2014 | FRAMING | BBENEDOI | Approved | IVRS - Inspection :* |
04/21/2015 | FIRE - FINAL | nsprenger | Approved | |
04/29/2015 | ELECTRIC - FINAL | BBENEDOI | Approved | IVRS - Inspection :* |
04/29/2015 | ELECTRIC - OUTDOOR LIGHTING | BBENEDOI | Approved | IVRS - Inspection :* |
04/29/2015 | ELECTRIC - PROGRESS | BBENEDOI | Approved | IVRS - Inspection :* |
04/29/2015 | ELECTRIC - UFER | BBENEDOI | Approved | IVRS - Inspection :* |
04/29/2015 | BUILDING - PROGRESS | BBENEDOI | Approved | IVRS - Inspection :* |
04/29/2015 | SHEET ROCK NAILING | BBENEDOI | Approved | IVRS - Inspection :* |
04/29/2015 | ROOF NAILING | BBENEDOI | Approved | IVRS - Inspection :* |
05/11/2015 | MECHANICAL - FINAL | JBURGE | Approved | IVRS - Inspection :* |
05/11/2015 | PLUMBING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
05/11/2015 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |