Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T13CM06766
Permit Details
Apply Date:
11/05/2013
Applicant:
REYES ARVAYO
Description:
NEW SFR
Permit Reviews
Permit Number - T13CM06766
Permit Status: C of o
Permit Description: NEW SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/31/2014 | RESIDENTIAL - BLDG/WWM | 02/10/2014 | COMPLETED |
11/05/2013 | PLANS OK TO SUBMIT - RES | 12/27/2013 | COMPLETED |
12/27/2013 | PLANS OK TO SUBMIT - RES | 12/27/2013 | COMPLETED |
12/30/2013 | RESIDENTIAL - BLDG/WWM | 01/27/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM06766
Permit Status: C of o
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/05/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM06766
Permit Description: NEW SFR
Total Completed Inspections - 27
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/11/2014 | ELECTRIC - UFER | DQUINN | Approved | |
02/11/2014 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
02/19/2014 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | HCS IS ACTUALLY 3" ABS CONNECTION TO EXISTING DRAIN LINE ON SOUTH SIDE OF NEW HOUSE |
02/19/2014 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | |
02/19/2014 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
02/21/2014 | BUILDING PRE-SLAB | RMYERS | Approved | |
02/28/2014 | REINFORCED MASONRY PRE-GROUT | DQUINN | Approved | |
03/07/2014 | ROOF NAILING | DQUINN | Approved | |
03/07/2014 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
03/17/2014 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
03/17/2014 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | |
03/17/2014 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
03/17/2014 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
03/17/2014 | U VALUE FOR WINDOW | DQUINN | Approved | |
03/17/2014 | FRAMING | DQUINN | Approved | |
03/17/2014 | STUCCO MESH | DQUINN | Approved | |
03/25/2014 | SHEET ROCK NAILING | DQUINN | Approved | |
04/01/2014 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | |
04/01/2014 | ELECTRIC - CABLE DROP | DQUINN | Approved | |
04/02/2014 | TEP CLEARANCE - AM | DQUINN | Approved | ECO |
05/16/2014 | MECHANICAL - FINAL | DQUINN | Approved | |
05/16/2014 | PLUMBING - FINAL | DQUINN | Approved | |
05/16/2014 | PLUMBING - GAS PRESS TEST FNL | DQUINN | Approved | |
05/16/2014 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
05/16/2014 | ELECTRIC - FINAL | DQUINN | Approved | |
05/16/2014 | BUILDING - FINAL | DQUINN | Approved | |
05/19/2014 | GAS CLEARANCE | DQUINN | Approved | 1 |