Permit Reviews
Permit Number - T13CM06759
Permit Status: C of o
Permit Description: EDUCATION BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/06/2014 | RESUBMITTAL | 01/17/2014 | COMPLETED |
| 01/17/2014 | RESUBMITTAL | 01/23/2014 | COMPLETED |
| 01/23/2014 | RESUBMITTAL | 01/28/2014 | COMPLETED |
| 01/28/2014 | RESUBMITTAL | 01/29/2014 | ACTIVE |
| 11/05/2013 | PLANS OK TO SUBMIT - COMM | 11/05/2013 | COMPLETED |
| 11/05/2013 | COMMERCIAL - TI | 12/19/2013 | COMPLETED |
| 12/19/2013 | RESUBMITTAL - TI ALL | 01/06/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM06759
Permit Status: C of o
Permit Description: EDUCATION BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/05/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM06759
Permit Description: EDUCATION BUILDING
Total Completed Inspections - 35
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/11/2014 | ELECTRIC - UNDERGROUND | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/26/2014 | PLUMBING - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/28/2014 | PLUMBING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/11/2014 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/28/2014 | NPPO - FINAL | MRUSSO | Approved | |
| 03/28/2014 | SIGN - FINAL | MRUSSO | Approved | |
| 03/28/2014 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 03/28/2014 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 04/01/2014 | MECHANICAL - ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/01/2014 | MECHANICAL - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/01/2014 | PLUMBING - ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/01/2014 | PLUMBING - PRE SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/01/2014 | PLUMBING - ROUGH, SOIL | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/01/2014 | ELECTRIC - TEMPORARY SERVICE | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/01/2014 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/01/2014 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/03/2014 | FIRE SPKLR - FINAL | CBASALDU | Approved | |
| 04/04/2014 | FIRE - ALARM FINAL | CBASALDU | Approved | |
| 04/04/2014 | ELECTRIC - ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/04/2014 | ELECTRIC - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/08/2014 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/08/2014 | ELECTRIC - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/16/2014 | MECHANICAL - FINAL | RMYERS | Approved | |
| 04/16/2014 | MECHANICAL - FINAL | RMYERS | Approved | |
| 04/16/2014 | PLUMBING - FINAL | RMYERS | Approved | |
| 04/16/2014 | ELECTRIC - PROGRESS | RMYERS | Approved | |
| 04/16/2014 | ELECTRIC - UFER | RMYERS | Approved | |
| 04/23/2014 | RIGHT OF WAY - FINAL | TWOLFGAN | Approved | |
| 04/23/2014 | FIRE - FINAL | CBASALDU | Approved | |
| 04/24/2014 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/30/2014 | FIRE SPKLR - UG, PIPING, HYDRO | WMOTTO | Approved | |
| 04/30/2014 | FIRE - LANE SIGNS | CBASALDU | Approved | |
| 04/30/2014 | FIRE - HYDRANTS | CBASALDU | Approved | |
| 04/30/2014 | FIRE SPKLR - OH PIPING & HYDRO | CBASALDU | Approved | |
| 04/30/2014 | FIRE SPKLR - UG PIPING FLUSH | CBASALDU | Approved |