Permit Details

Status:
Expired
Type:
COMMERCIAL ALTERATION
Address:
2526 E 6TH ST
Apply Date:
10/07/2013
Applicant:
N/A
Description:
BAKERY
Architects:
  • DANNY QUIHUIS

Permit Reviews

Permit Number - T13CM06126
Permit Status: Expired
Permit Description: BAKERY
Start Date Submittal Complete Date Status  
11/22/2013 COMMERCIAL - TI 11/25/2013 COMPLETED Review Details
11/25/2013 COMMERCIAL - TI 03/13/2014 ACTIVE Review Details

Outstanding Activity Conditions

Permit Number - T13CM06126
Permit Status: Expired
Permit Description: BAKERY
Total Outstanding Activity Conditions - 1
Date Name
10/07/2013 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Expired
Permit Number: T13CM06126
Permite Description: BAKERY
Total Outstanding Inspections - 7
Last Inspection Date Description Inspector Results Comments
FRAMING N/A Not Inspected
ELECTRIC - INTERMEDIATE N/A Not Inspected
PLUMBING - PROGRESS N/A Not Inspected
MECHANICAL - INTERMEDIATE N/A Not Inspected
MECHANICAL - ABOVE CEILING N/A Not Inspected
10/07/2014 MECHANICAL - HOODS N/A Partial Approval IVRS - Inspection :*
10/07/2014 MECHANICAL - HOODS N/A Partial Approval SMOKE TEST COMPLETE OK TO FINISH WRAP

Completed Inspections

Permit Status: Expired
Permit Number: T13CM06126
Permit Description: BAKERY
Total Completed Inspections - 12
Date Description Inspector Results Comments
07/14/2014 PLUMBING - PRE SLAB MRAMBER Approved IVRS - Inspection :*
07/16/2014 PLUMBING - ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
07/16/2014 PLUMBING - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
07/16/2014 PLUMBING - ROUGH, SOIL MRAMBER Approved IVRS - Inspection :*
07/21/2014 PLUMBING - FINAL BSTEVENS Approved ALL PLUMBING IS OK BUT WILL BE WITHELD PENDING OTHER FINALS
07/21/2014 PLUMBING - GAS PRESSURE TEST BSTEVENS Approved
11/18/2014 ELECTRIC - FINAL MPUGH Approved IVRS - Inspection :*
12/05/2014 FIRE - FINAL wmotto1 Approved 1. need to remove all extension cords used for permanet power source.

2. need 2a10bc fire extinguisher mounted.

3. Need sign over main door stating this door to remain unlocked during buisness hours.

4. kitchen hood still needs to be tested has not passed mechanical.
12/05/2014 FIRE - KITCHEN EXH HOOD FINAL wmotto1 Approved 1. mechanical inspector has not approved the hood.
12/23/2014 MECHANICAL - FINAL JMILITELLO Approved PROVIDE A DOME STRAINER AT FLOOR SINK. PROVIDE A MIXING VALVE AT HAND SINK. AIR BALANCE & CAPTURE TESTS ARE OK. PROVIDE ACCESS TO ROOF. PROVIDE STERILIZATION REPORT.
12/23/2014 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
01/12/2015 BUILDING - FINAL JMILITEL Approved IVRS - Inspection :*

Documents

File Name Document Type  
001_T1.1.TIF CONSTRPLANS VIEW
002_A1.1.TIF CONSTRPLANS VIEW
003_A1.2.TIF CONSTRPLANS VIEW
004_M1.1.TIF CONSTRPLANS VIEW
005_M2.1.TIF CONSTRPLANS VIEW
006_M3.1.TIF CONSTRPLANS VIEW
007_P1.1.TIF CONSTRPLANS VIEW
008_P2.1.TIF CONSTRPLANS VIEW
009_E1.0.TIF CONSTRPLANS VIEW
010_E2.0.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW