Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T13CM05220
Permit Details
Apply Date:
08/22/2013
Applicant:
THOMAS CHASTY
Description:
EXTERIOR RENOVATION OF EXISTING MOB AND NEW CANOPY, INTERIOR RENOVATION OF EXISTING LOBBY.
Architects:
- HOBBS, WILLIAM SAMUEL
Contractors:
- BARKER MORRISSEY CONTRACTING INC **APA**
Permit Reviews
Permit Number - T13CM05220
Permit Status: L of c
Permit Description: EXTERIOR RENOVATION OF EXISTING MOB AND NEW CANOPY, INTERIOR RENOVATION OF EXISTING LOBBY.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/22/2013 | COMMERCIAL - TI | 09/04/2013 | COMPLETED |
| 09/04/2013 | COMMERCIAL - TI | 10/02/2013 | COMPLETED |
| 10/02/2013 | RESUBMITTAL | 10/15/2013 | COMPLETED |
| 10/15/2013 | RESUBMITTAL | 03/07/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM05220
Permit Status: L of c
Permit Description: EXTERIOR RENOVATION OF EXISTING MOB AND NEW CANOPY, INTERIOR RENOVATION OF EXISTING LOBBY.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/22/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T13CM05220
Permit Description: EXTERIOR RENOVATION OF EXISTING MOB AND NEW CANOPY, INTERIOR RENOVATION OF EXISTING LOBBY.
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/13/2014 | BUILDING PRE-SLAB | JMILITEL | Approved | OK TO POUR 7 COLUMN FOOTINGS & SLABS PENDING SPECIAL INSPECTION |
| 03/13/2014 | EXCAVATION/LAYOUT REBAR & ZON | JMILITEL | Approved | OK TO POUR 7 COLUMN FOOTINGS & SLABS PENDING SPECIAL INSPECTION |
| 03/13/2014 | BUILDING PRE-SLAB | JMILITEL | Approved | IVRS - Inspection :* |
| 03/13/2014 | EXCAVATION/LAYOUT REBAR & ZON | JMILITEL | Approved | IVRS - Inspection :* |
| 04/02/2014 | FRAMING | DQUINN | Approved | COLUMN CHASE FRAMES OK TO COVER |
| 04/15/2014 | STUCCO MESH | MPUGH | Approved | IVRS - Inspection :* |
| 04/15/2014 | EXT METAL CLIPS/EXT SHEATHING | MPUGH | Approved | IVRS - Inspection :* |
| 04/15/2014 | ROOF NAILING | MPUGH | Approved | IVRS - Inspection :* |
| 05/09/2014 | ELECTRIC - UNDERGROUND | JMILITEL | Approved | IVRS - Inspection :* |
| 05/09/2014 | REINFORCED MASONRY PRE-GROUT | JMILITEL | Approved | IVRS - Inspection :* |
| 05/09/2014 | STEM WALL/RETAINING WALL | JMILITEL | Approved | IVRS - Inspection :* |
| 05/15/2014 | SHEET ROCK NAILING | JMILITEL | Approved | ELEC IN SOFFIT AT 1ST FLOOR LOBBY OK TO SHEETROCK & TAPE |
| 05/15/2014 | SHEET ROCK NAILING | JMILITEL | Approved | IVRS - Inspection :* |
| 05/15/2014 | ELECTRIC - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 05/15/2014 | SIGN - FINAL | RLEDONNE | Approved | |
| 05/16/2014 | NPPO - FINAL | RLEDONNE | Approved | |
| 05/29/2014 | BUILDING ABOVE CEILING | JMILITEL | Approved | 2ND FLOOR LOBBY OK TO CLOSE CEILING |
| 05/29/2014 | ELECTRIC - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 05/29/2014 | ELECTRIC - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 05/29/2014 | BUILDING ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 06/04/2014 | FIRE SPKLR - FINAL | CBASALDU | Approved | |
| 06/04/2014 | U VALUE FOR WINDOW | JMILITEL | Approved | IVRS - Inspection :* |
| 08/01/2014 | FIRE - FINAL | WMOTTO | Approved | |
| 08/01/2014 | FIRE - ALARM FINAL | WMOTTO | Approved | |
| 08/01/2014 | BUILDING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 08/01/2014 | BUILDING - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 08/01/2014 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
| 08/04/2014 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 08/04/2014 | ENGINEERING - FINAL | RLEDONNE | Approved |