Permit: T13CM04620
Permit Details
Apply Date:
07/29/2013
Applicant:
N/A
Description:
NEW SFR
Contractors:
- ZERILLI CONSTUCTION LLC
Permit Reviews
Permit Number - T13CM04620
Permit Status: Final
Permit Description: NEW SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/28/2014 | REVISION - - 2ND | 01/28/2014 | COMPLETED |
07/29/2013 | PLANS OK TO SUBMIT - RES | 08/01/2013 | COMPLETED |
08/01/2013 | RESIDENTIAL - BLDG/WWM | 08/28/2013 | COMPLETED |
09/18/2013 | RESUBMITTAL | 09/26/2013 | COMPLETED |
09/26/2013 | RESUBMITTAL | 10/02/2013 | COMPLETED |
11/12/2013 | REVISION - - 1ST | 11/12/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM04620
Permit Status: Final
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/29/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T13CM04620
Permit Description: NEW SFR
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/11/2013 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | |
10/17/2013 | ELECTRIC - UFER | MRAMBER | Approved | IVRS - Inspection :* |
10/17/2013 | BUILDING PRE-SLAB | MRAMBER | Approved | IVRS - Inspection :* |
10/17/2013 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | IVRS - Inspection :* |
10/31/2013 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | 1. 4" SDR-35 from main to property line OK to cover. |
12/03/2013 | ROOF NAILING | MPUGH | Approved | IVRS - Inspection :* |
12/03/2013 | EXT METAL CLIPS/EXT SHEATHING | MPUGH | Approved | IVRS - Inspection :* |
12/20/2013 | PLUMBING - INTERMEDIATE | RMYERS | Approved | 1. Need to see closet flange. |
12/20/2013 | MECHANICAL - INTERMEDIATE | RMYERS | Approved | |
12/20/2013 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | |
12/20/2013 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | |
12/20/2013 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | |
12/20/2013 | ELECTRIC - INTERMEDIATE | RMYERS | Approved | |
12/20/2013 | U VALUE FOR WINDOW | RMYERS | Approved | |
12/20/2013 | STUCCO MESH | RMYERS | Approved | |
12/20/2013 | FRAMING | RMYERS | Approved | |
01/30/2014 | ELECTRIC - TEMPORARY SERVICE | MPUGH | Approved | IVRS - Inspection :* |
01/31/2014 | TEP CLEARANCE - AM | MPUGH | Approved | TEC |
02/06/2014 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
02/25/2014 | SHEET ROCK NAILING | RMYERS | Approved | |
03/13/2014 | MECHANICAL - FINAL | MPUGH | Approved | IVRS - Inspection :* |
03/13/2014 | PLUMBING - FINAL | MPUGH | Approved | IVRS - Inspection :* |
03/13/2014 | OUTDOOR LIGHTING FINAL | MPUGH | Approved | IVRS - Inspection :* |
03/13/2014 | ELECTRIC - FINAL | MPUGH | Approved | IVRS - Inspection :* |
03/20/2014 | BUILDING - FINAL | MPUGH | Approved | IVRS - Inspection :* |