Permit: T13CM04427
Permit Details
Apply Date:
07/19/2013
Applicant:
TONY BUCK
Description:
NEW SFR
Contractors:
- MCCALEB CONSTRUCTION LLC
Permit Reviews
Permit Number - T13CM04427
Permit Status: C of o
Permit Description: NEW SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/19/2013 | PLANS OK TO SUBMIT - RES | 07/22/2013 | COMPLETED |
| 07/22/2013 | RESIDENTIAL - BLDG/WWM | 08/16/2013 | COMPLETED |
| 08/20/2013 | RESIDENTIAL - BLDG/WWM | 08/26/2013 | COMPLETED |
| 11/08/2013 | REVISION - - 1ST | 11/26/2013 | ACTIVE |
| 11/08/2013 | REVISION - WALK THRU | 11/08/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM04427
Permit Status: C of o
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/19/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM04427
Permit Description: NEW SFR
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/03/2013 | ELECTRIC - UFER | DQUINN | Approved | garage stup-up ok |
| 09/06/2013 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | BASEMENT FOOTINGS & SLEEVES OK |
| 09/06/2013 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | IVRS - Inspection :* |
| 09/23/2013 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | |
| 09/23/2013 | ELECTRIC - CABLE DROP | DQUINN | Approved | |
| 09/24/2013 | TEP CLEARANCE - AM | DQUINN | Approved | ECO |
| 09/27/2013 | REINFORCED MASONRY PRE-GROUT | BSTEVENS | Approved | OK TO TOP-OUT |
| 09/27/2013 | REINFORCED MASONRY PRE-GROUT | BSTEVENS | Approved | IVRS - Inspection :* |
| 10/15/2013 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | ROUGH FOR MASTER BATH2, BATH 3, GARAGE KITCHEN AND BATH AND BBQ SINK ARE ALL OK TO BACKFILL SOUTH TO BATH 3 |
| 10/17/2013 | BUILDING PRE-SLAB | DQUINN | Approved | |
| 11/15/2013 | ROOF NAILING | BSTEVENS | Approved | |
| 11/26/2013 | MECHANICAL - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
| 11/26/2013 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
| 11/26/2013 | ELECTRIC - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
| 11/26/2013 | U VALUE FOR WINDOW | RMYERS | Approved | IVRS - Inspection :* |
| 11/26/2013 | FRAMING | RMYERS | Approved | IVRS - Inspection :* |
| 12/10/2013 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* |
| 12/11/2013 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | |
| 12/18/2013 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | |
| 03/11/2014 | ELECTRIC - FINAL | BSTEVENS | Approved | |
| 03/11/2014 | OUTDOOR LIGHTING FINAL | BSTEVENS | Approved | |
| 03/11/2014 | PLUMBING - FINAL | BSTEVENS | Approved | |
| 03/11/2014 | PLUMBING - GAS PRESS TEST FNL | BSTEVENS | Approved | |
| 03/11/2014 | MECHANICAL - FINAL | BSTEVENS | Approved | |
| 04/01/2014 | BUILDING - FINAL | BSTEVENS | Approved | IVRS - Inspection :* |