Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Address NEW:
118 E CONGRESS ST
Apply Date:
06/05/2013
Applicant:
FRANK LIETZAU
Description:
RESTAURANT /WINE BAR
Contractors:
  • CORONA SIERRA INC ,

Permit Reviews

Permit Number - T13CM03395
Permit Status: C of o
Permit Description: RESTAURANT /WINE BAR
Start Date Submittal Complete Date Status  
06/05/2013 COMMERCIAL - TI 06/11/2013 COMPLETED Review Details
06/11/2013 WALK THRU - COMM 06/11/2013 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T13CM03395
Permit Status: C of o
Permit Description: RESTAURANT /WINE BAR
Total Outstanding Activity Conditions - 1
Date Name
06/05/2013 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T13CM03395
Permit Description: RESTAURANT /WINE BAR
Total Completed Inspections - 24
Date Description Inspector Results Comments
07/19/2013 ELECTRIC - INTERMEDIATE LHANLY Approved
07/19/2013 FRAMING LHANLY Approved
08/14/2013 ELECTRIC - ABOVE CEILING LHANLY Approved
08/14/2013 MECHANICAL - ABOVE CEILING LHANLY Approved
08/14/2013 MECHANICAL - INTERMEDIATE LHANLY Approved
08/14/2013 PLUMBING - PROGRESS LHANLY Approved
08/14/2013 PLUMBING - ABOVE CEILING LHANLY Approved
08/14/2013 PLUMBING - INTERMEDIATE LHANLY Approved
08/14/2013 PLUMBING - PRE SLAB LHANLY Approved
08/14/2013 PLUMBING - ROUGH, SOIL LHANLY Approved
08/14/2013 SHEET ROCK NAILING LHANLY Approved
08/14/2013 BUILDING ABOVE CEILING LHANLY Approved
08/14/2013 RIGHT OF WAY - FINAL LHANLY Approved
08/14/2013 NPPO - FINAL LHANLY Approved
08/14/2013 SIGN - FINAL LHANLY Approved
08/14/2013 LANDSCAPE - FINAL LHANLY Approved
08/14/2013 ENGINEERING - FINAL LHANLY Approved
09/09/2013 ELECTRIC - FINAL LHANLY Approved
09/09/2013 MECHANICAL - FINAL LHANLY Approved
09/09/2013 PLUMBING - FINAL LHANLY Approved
09/12/2013 FIRE SPKLR - FINAL wmotto Approved
09/13/2013 FIRE - FINAL wmotto Approved
09/13/2013 BUILDING - FINAL LHANLY Approved OK FOR TCO WITH FIRE FINAL. AIR DUCTING TO BE MODIFIED FOR MORE O.A.
02/04/2014 HEALTH DEPT - FINAL 724-7908 PCHEALTH Approved