Permit: T13CM02056
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
6620 S MEMORIAL PL #100
Address NEW:
6620 S MEMORIAL PL #100
Apply Date:
04/09/2013
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: OFFICE/WAREHOUSE
Contractors:
- BARKER MORRISSEY CONTRACTING INC **APA**
Permit Reviews
Permit Number - T13CM02056
Permit Status: C of o
Permit Description: TI: OFFICE/WAREHOUSE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/09/2013 | PLANS OK TO SUBMIT - COMM | 04/10/2013 | COMPLETED |
| 04/10/2013 | COMMERCIAL - TI | 04/26/2013 | COMPLETED |
| 04/26/2013 | RESUBMITTAL - TI ALL | 05/01/2013 | COMPLETED |
| 05/03/2013 | REVISION - - 1ST | 05/08/2013 | COMPLETED |
| 06/07/2013 | REVISION - - 2ND | 06/07/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM02056
Permit Status: C of o
Permit Description: TI: OFFICE/WAREHOUSE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/09/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM02056
Permit Description: TI: OFFICE/WAREHOUSE
Total Completed Inspections - 33
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/02/2013 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | 7 EACH COLUMN FOOTINGS: 2-C1/F2; 5 C1/F1- OK TO POUR PROGRESS AREAS |
| 05/02/2013 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* |
| 05/10/2013 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 05/10/2013 | SIGN - FINAL | MRUSSO | Approved | |
| 05/10/2013 | NPPO - FINAL | MRUSSO | Approved | |
| 05/20/2013 | FRAMING | JBURGE | Approved | ALL WALLS & INTERIOR DECKING THROUGHOUT - OK TO COVER |
| 05/20/2013 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 05/30/2013 | ELECTRIC - UNDERGROUND | JBURGE | Approved | IVRS - Inspection :* |
| 06/06/2013 | PLUMBING - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 06/06/2013 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 06/07/2013 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
| 06/12/2013 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 06/12/2013 | PLUMBING - PRE SLAB | JBURGE | Approved | IVRS - Inspection :* |
| 06/12/2013 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | IVRS - Inspection :* |
| 06/18/2013 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | ROOMS #175A - 175B |
| 06/18/2013 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 06/24/2013 | PLUMBING - ABOVE CEILING | JBURGE | Approved | OK TO SET CEILING TILES |
| 06/24/2013 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | SWITCHES FOR HEPA FILTERS |
| 06/24/2013 | PLUMBING - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 06/24/2013 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 06/28/2013 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 06/28/2013 | PLUMBING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 06/28/2013 | PLUMBING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 06/28/2013 | ELECTRIC - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 06/28/2013 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 06/28/2013 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 06/28/2013 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* |
| 06/28/2013 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 07/03/2013 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
| 07/05/2013 | FIRE - FINAL | WMOTTO | Approved | |
| 07/05/2013 | FIRE - ALARM FINAL | WMOTTO | Approved | |
| 07/17/2013 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 07/17/2013 | MECHANICAL - FINAL | JBURGE | Approved | IVRS - Inspection :* |