Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T13CM00621
Permit Details
Apply Date:
02/01/2013
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
RETAIL
Contractors:
- KROLL CONTRACTORS INC
Permit Reviews
Permit Number - T13CM00621
Permit Status: C of o
Permit Description: RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/01/2013 | COMMERCIAL - TI | 02/07/2013 | COMPLETED |
02/12/2013 | RESUBMITTAL | 02/21/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM00621
Permit Status: C of o
Permit Description: RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/01/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM00621
Permit Description: RETAIL
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/12/2013 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
03/12/2013 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
04/08/2013 | PLUMBING - ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
04/29/2013 | MECHANICAL - ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
04/29/2013 | MECHANICAL - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
04/29/2013 | PLUMBING - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
05/02/2013 | ELECTRIC - ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
05/02/2013 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
05/14/2013 | ELECTRIC - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
06/07/2013 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
06/24/2013 | BUILDING ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
06/24/2013 | MECHANICAL - FINAL | MPUGH | Approved | IVRS - Inspection :* |
06/27/2013 | NPPO - FINAL | DROBERTS | Approved | |
06/27/2013 | SIGN - FINAL | DROBERTS | Approved | |
06/27/2013 | LANDSCAPE - FINAL | DROBERTS | Approved | |
06/27/2013 | ENGINEERING - FINAL | DROBERTS | Approved | |
06/27/2013 | ELECTRIC - FINAL | MPUGH | Approved | IVRS - Inspection :* |
06/27/2013 | PLUMBING - FINAL | MPUGH | Approved | IVRS - Inspection :* |
06/27/2013 | BUILDING - FINAL | MPUGH | Approved | IVRS - Inspection :* |
06/28/2013 | FIRE - FINAL | WMOTTO | Approved | PER FINAL |
06/28/2013 | RIGHT OF WAY - FINAL | BESPINO | Approved | PER IN PERSON |
06/28/2013 | FIRE - FINAL | wmotto | Approved | |
06/28/2013 | PLUMBING - PROGRESS | MPUGH | Approved | PER FINAL |
06/28/2013 | ELECTRIC - UFER | MPUGH | Approved | PER FINAL |
06/28/2013 | ELECTRIC - SERVICE UPGRADE | MPUGH | Approved | PER FINAL |