Permit: T13CM00574
Permit Details
Status:
Final
Type:
COMMERCIAL ALTERATION
Address:
5102 E SPEEDWAY BL
Address NEW:
5102 E SPEEDWAY BL
Apply Date:
01/31/2013
Applicant:
N/A
Description:
TI: SHELL IMPROVEMENTS
Architects:
- VOGEL, BENJAMIN ARMANDO
Contractors:
- STEEL DESIGN AND CONSTRUCTION
Permit Reviews
Permit Number - T13CM00574
Permit Status: Final
Permit Description: TI: SHELL IMPROVEMENTS
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/31/2013 | COMMERCIAL - TI | 02/01/2013 | COMPLETED |
| 02/01/2013 | COMMERCIAL - TI | 02/01/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM00574
Permit Status: Final
Permit Description: TI: SHELL IMPROVEMENTS
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/31/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T13CM00574
Permit Description: TI: SHELL IMPROVEMENTS
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/21/2013 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | |
| 02/21/2013 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | ADD NEW SERVICE SINK ON WEST SIDE OF PLUMBING WALL TO AP PLANS. HOSE BIBBI ON SOUTH WALL ON AP PLANS HAS NOT BEEN INSTALLED. |
| 02/21/2013 | PLUMBING - PRE SLAB | RLEDONNE | Approved | |
| 02/21/2013 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | |
| 02/28/2013 | ELECTRIC - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 02/28/2013 | ELECTRIC - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 02/28/2013 | BUILDING ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 02/28/2013 | FRAMING | JMILITEL | Approved | IVRS - Inspection :* |
| 03/12/2013 | SHEET ROCK NAILING | JMILITEL | Approved | IVRS - Inspection :* |
| 07/10/2013 | ELECTRIC - OUTDOOR LIGHTING | JMILITEL | Approved | IVRS - Inspection :* |
| 07/10/2013 | ELECTRIC - SERVICE UPGRADE | JMILITEL | Approved | IVRS - Inspection :* |
| 07/11/2013 | TEP CLEARANCE - AM | JMILITEL | Approved | ECO A &B |
| 07/30/2013 | OUTDOOR LIGHTING FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 07/30/2013 | ELECTRIC - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 07/30/2013 | FIRE - FINAL | WMOTTO | Approved | |
| 07/30/2013 | FIRE - ALARM FINAL | WMOTTO | Approved | |
| 07/30/2013 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
| 07/31/2013 | NPPO - FINAL | RLEDONNE | Approved | |
| 07/31/2013 | SIGN - FINAL | RLEDONNE | Approved | |
| 07/31/2013 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 07/31/2013 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 08/06/2013 | MECHANICAL - INTERMEDIATE | JMILITELLO | Approved | |
| 08/06/2013 | MECHANICAL - FINAL | JMILITELLO | Approved | |
| 08/06/2013 | PLUMBING - ABOVE CEILING | JMILITELLO | Approved | |
| 08/06/2013 | PLUMBING - PROGRESS | JMILITELLO | Approved | |
| 08/06/2013 | PLUMBING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 08/06/2013 | BUILDING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |