Permit: T12CM08252
Permit Details
Apply Date:
12/31/2012
Applicant:
N/A
Description:
RESTAURANT
Architects:
- FUENTEVILLA, MIGUEL RAUL
Contractors:
- HOPE CONSTRUCTION L L C
Permit Reviews
Permit Number - T12CM08252
Permit Status: C of o
Permit Description: RESTAURANT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/07/2013 | COMMERCIAL - TI | 02/15/2013 | COMPLETED |
03/18/2013 | RESUBMITTAL | 03/27/2013 | COMPLETED |
03/27/2013 | RESUBMITTAL | 04/01/2013 | COMPLETED |
04/01/2013 | RESUBMITTAL | 04/02/2013 | ACTIVE |
12/31/2012 | PLANS OK TO SUBMIT - COMM | 01/03/2013 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM08252
Permit Description: RESTAURANT
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/17/2013 | TEP CLEARANCE - AM | LHANLY | Approved | ECO LOCKOUT TAGOUT IN PLACE |
04/18/2013 | MECHANICAL - HOODS | LHANLY | Approved | |
04/18/2013 | PLUMBING - GAS PRESSURE TEST | LHANLY | Approved | |
04/18/2013 | PLUMBING - YARD WTR LINE/TEST | LHANLY | Approved | |
04/18/2013 | PLUMBING - ABOVE CEILING | LHANLY | Approved | |
04/18/2013 | PLUMBING - INTERMEDIATE | LHANLY | Approved | |
04/18/2013 | PLUMBING - PRE SLAB | LHANLY | Approved | |
04/18/2013 | PLUMBING - ROUGH, SOIL | LHANLY | Approved | |
04/18/2013 | SHEET ROCK NAILING | LHANLY | Approved | |
04/18/2013 | BUILDING ABOVE CEILING | LHANLY | Approved | |
04/18/2013 | FRAMING | LHANLY | Approved | |
04/18/2013 | MECHANICAL - HYDRONIC PIPING | LHANLY | Approved | |
04/18/2013 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
04/18/2013 | ELECTRIC - UNDERGROUND | LHANLY | Approved | |
05/02/2013 | FIRE - FINAL | WMOTTO | Approved | |
05/02/2013 | FIRE - KITCHEN EXH HOOD FINAL | WMOTTO | Approved | |
05/02/2013 | FIRE - ALARM FINAL | WMOTTO | Approved | |
05/02/2013 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
05/02/2013 | PLUMBING - FINAL | LHANLY | Approved | |
05/02/2013 | PLUMBING - PROGRESS | LHANLY | Approved | |
05/02/2013 | BUILDING - PROGRESS | LHANLY | Approved | |
05/02/2013 | MECHANICAL - FINAL | LHANLY | Approved | |
05/02/2013 | MECHANICAL - ABOVE CEILING | LHANLY | Approved | |
05/02/2013 | MECHANICAL - INTERMEDIATE | LHANLY | Approved | |
05/02/2013 | ELECTRIC - SERVICE UPGRADE | LHANLY | Approved | |
05/02/2013 | ELECTRIC - ABOVE CEILING | LHANLY | Approved | |
05/02/2013 | ELECTRIC - FINAL | LHANLY | Approved | |
05/09/2013 | BUILDING - FINAL | LHANLY | Approved |