Permit: T12CM08198
Permit Details
Apply Date:
12/27/2012
Applicant:
RAWSON, RHONDA LEE
Description:
TI: OFFICE
Architects:
- RAWSON, RHONDA LEE
Contractors:
- M A S DEVELOPMENT INC *APA*
Permit Reviews
Permit Number - T12CM08198
Permit Status: L of c
Permit Description: TI: OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
12/27/2012 | COMMERCIAL - TI | 01/02/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM08198
Permit Status: L of c
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/27/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T12CM08198
Permit Description: TI: OFFICE
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/05/2013 | PLUMBING - PRE SLAB | MRAMBER | Approved | IVRS - Inspection :*MAKE SURE BUBBLE WRAP EXTENDS ABOVE FINISHED SLAB |
02/27/2013 | PLUMBING - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
03/04/2013 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
03/08/2013 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
03/08/2013 | FRAMING | DSANTACR | Approved | IVRS - Inspection :* |
03/12/2013 | BUILDING ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
03/12/2013 | MECHANICAL - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
06/17/2013 | ELECTRIC - TEMP POWER FOR TEST | MRAMBER | Approved | IVRS - Inspection :* |
06/18/2013 | TEP CLEARANCE - AM | MRAMBER | Approved | TEC 106 |
07/18/2013 | PLUMBING - ABOVE CEILING | MRAMBER | Approved | |
07/18/2013 | PLUMBING - GAS PRESSURE TEST | MRAMBER | Approved | |
07/18/2013 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | |
07/18/2013 | PLUMBING - PROGRESS | MRAMBER | Approved | |
07/18/2013 | PLUMBING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
07/18/2013 | ELECTRIC - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
07/24/2013 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | |
07/24/2013 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
07/24/2013 | FIRE - FINAL | wmotto | Approved | |
07/26/2013 | SHEET ROCK NAILING | MRAMBER | Approved | |
07/26/2013 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |