Permit: T12CM08111
Permit Details
Status:
Final
Type:
SINGLE FAMILY ADDITION
Address:
6725 E CALLE DENED
Address NEW:
6725 E CALLE DENED
Apply Date:
12/21/2012
Applicant:
JW ADRAGNA COMPANY
Description:
REMODEL; BATHROOM. ADDITION; BEDROOM, BATHROOM, STORAGE, NEW PORCH. ENCLOSE CARPORT INTO LIVEABLE SPACE
Architects:
- JW ADRAGNA COMPANY
Outstanding Activity Conditions
Permit Number - T12CM08111
Permit Status: Final
Permit Description: REMODEL; BATHROOM. ADDITION; BEDROOM, BATHROOM, STORAGE, NEW PORCH. ENCLOSE CARPORT INTO LIVEABLE SPACE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/21/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T12CM08111
Permit Description: REMODEL; BATHROOM. ADDITION; BEDROOM, BATHROOM, STORAGE, NEW PORCH. ENCLOSE CARPORT INTO LIVEABLE SPACE
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/25/2014 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | IVRS - Inspection :* |
| 05/22/2015 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* |
| 08/06/2015 | BUILDING PRE-SLAB | JBURGE | Approved | OK TO POUR SLAB |
| 08/06/2015 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* |
| 08/01/2016 | FRAMING | MPUGH1 | Approved | IVRS - Inspection :* |
| 10/19/2016 | ROOF NAILING | MPUGH1 | Approved | IVRS - Inspection :* |
| 11/08/2016 | EXT METAL CLIPS/EXT SHEATHING | MPUGH1 | Approved | IVRS - Inspection :* |
| 05/19/2017 | ELECTRIC - SERVICE UPGRADE | MPUGH1 | Approved | IVRS - Inspection :* |
| 05/23/2017 | TEP CLEARANCE - AM | MPUGH | Approved | INCR |
| 09/19/2017 | U VALUE FOR WINDOW | DQUINN | Approved | |
| 09/19/2017 | STUCCO MESH | DQUINN | Approved | |
| 04/30/2018 | BUILDING - FINAL | DQUINN | Approved | |
| 04/30/2018 | SHEET ROCK NAILING | DQUINN | Approved | |
| 04/30/2018 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
| 04/30/2018 | ELECTRIC - SERVICE RELOCATION | DQUINN | Approved | |
| 04/30/2018 | ELECTRIC - FINAL | DQUINN | Approved | |
| 04/30/2018 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
| 04/30/2018 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 04/30/2018 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | |
| 04/30/2018 | PLUMBING - FINAL | DQUINN | Approved | |
| 04/30/2018 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 04/30/2018 | MECHANICAL - FINAL | DQUINN | Approved | |
| 04/30/2018 | REINFORCED MASONRY PRE-GROUT | DQUINN | Approved |