Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
COMMERCIAL ALTERATION
Apply Date:
12/21/2012
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: RETAIL
Contractors:
  • DOUBLE A A BUILDERS LTD ,

Outstanding Activity Conditions

Permit Number - T12CM08105
Permit Status: Final
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 1
Date Name
12/21/2012 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T12CM08105
Permit Description: TI: RETAIL
Total Completed Inspections - 29
Date Description Inspector Results Comments
06/27/2013 FRAMING MRAMBER Approved IVRS - Inspection :*
07/01/2013 ELECTRIC - INTERMEDIATE MRAMBER Approved THIS IS FOR UNIT 203 & 203 WORK ROOM
07/01/2013 ELECTRIC - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
07/11/2013 PLUMBING - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
08/02/2013 SHEET ROCK NAILING MRAMBER Approved IVRS - Inspection :*
08/28/2013 MECHANICAL - ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
08/28/2013 PLUMBING - ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
08/28/2013 ELECTRIC - ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
08/28/2013 BUILDING ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
08/29/2013 TEP CLEARANCE - AM MRAMBER Approved TEC
09/18/2013 NPPO - FINAL RLEDONNE Approved
09/18/2013 SIGN - FINAL RLEDONNE Approved
09/18/2013 LANDSCAPE - FINAL RLEDONNE Approved
09/18/2013 MECHANICAL - FINAL MRAMBER Approved IVRS - Inspection :*
09/18/2013 MECHANICAL - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
09/18/2013 PLUMBING - PROGRESS MRAMBER Approved IVRS - Inspection :*
09/18/2013 PLUMBING - PRE SLAB MRAMBER Approved IVRS - Inspection :*
09/18/2013 PLUMBING - ROUGH, SOIL MRAMBER Approved IVRS - Inspection :*
09/18/2013 ELECTRIC - PROGRESS MRAMBER Approved IVRS - Inspection :*
09/18/2013 BUILDING - PROGRESS MRAMBER Approved IVRS - Inspection :*
09/19/2013 FIRE SPKLR - FINAL WMOTTO Approved
09/19/2013 FIRE - ALARM FINAL WMOTTO Approved
09/19/2013 ENGINEERING - FINAL RLEDONNE Approved
09/19/2013 FIRE - FINAL WMOTTO Approved
09/19/2013 RIGHT OF WAY - FINAL JC Approved
09/19/2013 ENGINEERING - FINAL RLEDONNE Approved SHELL NEEDS TO BE FINAL BEFORE TI FINAL.
09/20/2013 PLUMBING - FINAL MRAMBER Approved
09/20/2013 ELECTRIC - FINAL MRAMBER Approved
09/20/2013 BUILDING - FINAL MRAMBER Approved

Documents

File Name Document Type  
None DOCUMENTS VIEW