Status:
Final
Type:
COMMERCIAL NEW
Address:
1031 N PARK AV
Address NEW:
1031 N PARK AV
Apply Date:
12/20/2012
Applicant:
N/A
Description:
FOUNDATION ONLY FOR NEW STUDENT HOUSING TOWER
Contractors:
  • BEAL DERKENNE CONSTRUCTION LLC

Permit Reviews

Permit Number - T12CM08078
Permit Status: Final
Permit Description: FOUNDATION ONLY FOR NEW STUDENT HOUSING TOWER
Start Date Submittal Complete Date Status  
01/15/2013 COMMERCIAL - NEW 02/22/2013 COMPLETED Review Details
02/22/2013 RESUBMITTAL 03/22/2013 COMPLETED Review Details
03/22/2013 RESUBMITTAL 04/26/2013 COMPLETED Review Details
12/20/2012 PLANS OK TO SUBMIT - COMM 12/20/2012 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T12CM08078
Permit Status: Final
Permit Description: FOUNDATION ONLY FOR NEW STUDENT HOUSING TOWER
Total Outstanding Activity Conditions - 1
Date Name
12/20/2012 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T12CM08078
Permit Description: FOUNDATION ONLY FOR NEW STUDENT HOUSING TOWER
Total Completed Inspections - 25
Date Description Inspector Results Comments
06/27/2013 STEM WALL/RETAINING WALL MPUGH Approved CAST IN PLACE BASEMENT COLUMNS AND WALLS OK
06/27/2013 BUILDING - PROGRESS MPUGH Approved LEVEL P2 - OUR 1-4 AND RAMP UP LEVEL 1
EXTERIOR BASEMENT WALLS OK
TOWER CRANE FOOTING OK
06/27/2013 EXCAVATION/LAYOUT REBAR & ZON MPUGH Approved AS NOTED ON PLANS
06/27/2013 STEM WALL/RETAINING WALL MPUGH Approved IVRS - Inspection :*
06/27/2013 BUILDING - PROGRESS MPUGH Approved IVRS - Inspection :*
06/27/2013 EXCAVATION/LAYOUT REBAR & ZON MPUGH Approved IVRS - Inspection :*
09/09/2013 BUILDING PRE-SLAB LHANLY Approved LEVEL 4 SOUTH
01/31/2014 ELECTRIC - UFER MPUGH Approved IVRS - Inspection :*
01/31/2014 ELECTRIC - UNDERGROUND MPUGH Approved IVRS - Inspection :*
01/31/2014 ELECTRIC - INTERMEDIATE MPUGH Approved IVRS - Inspection :*
01/31/2014 ELECTRIC - ABOVE CEILING MPUGH Approved IVRS - Inspection :*
01/31/2014 ELECTRIC - FINAL MPUGH Approved IVRS - Inspection :*
01/31/2014 PLUMBING - ROUGH, SOIL MPUGH Approved IVRS - Inspection :*
01/31/2014 PLUMBING - INTERMEDIATE MPUGH Approved IVRS - Inspection :*
01/31/2014 PLUMBING - ROOF DRAINS MPUGH Approved IVRS - Inspection :*
01/31/2014 PLUMBING - YARD WTR LINE/TEST MPUGH Approved IVRS - Inspection :*
01/31/2014 PLUMBING - SEWER HCS CONNECT MPUGH Approved IVRS - Inspection :*
01/31/2014 SITE - SEWER MPUGH Approved IVRS - Inspection :*
01/31/2014 PLUMBING - PROGRESS MPUGH Approved IVRS - Inspection :*
01/31/2014 PLUMBING - FINAL MPUGH Approved IVRS - Inspection :*
01/31/2014 MECHANICAL - INTERMEDIATE MPUGH Approved IVRS - Inspection :*
01/31/2014 MECHANICAL - FINAL MPUGH Approved IVRS - Inspection :*
07/30/2014 BUILDING - FINAL MPUGH Approved IVRS - Inspection :*
07/31/2014 FIRE SPKLR - FINAL kenb Approved