Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T12CM07648
Permit Details
Apply Date:
12/04/2012
Applicant:
N/A
Description:
NEW BANK BUILDING
Contractors:
- DIMENSION DEVELOPMENT LLC
Permit Reviews
Permit Number - T12CM07648
Permit Status: C of o
Permit Description: NEW BANK BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/18/2013 | RESUBMITTAL | 02/20/2013 | COMPLETED |
02/20/2013 | RESUBMITTAL | 03/27/2013 | COMPLETED |
07/15/2013 | REVISION - - 1ST | 07/15/2013 | COMPLETED |
12/04/2012 | PLANS OK TO SUBMIT - COMM | 12/04/2012 | COMPLETED |
12/04/2012 | COMMERCIAL - NEW | 01/18/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM07648
Permit Status: C of o
Permit Description: NEW BANK BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/04/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM07648
Permit Description: NEW BANK BUILDING
Total Completed Inspections - 50
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/15/2013 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | PLEASE POST YOUR ADDRESS |
04/15/2013 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* |
04/24/2013 | ELECTRIC - UFER | JBURGE | Approved | IVRS - Inspection :* |
04/25/2013 | FIRE SPKLR - UG, PIPING, HYDRO | CBASALDU | Approved | |
04/29/2013 | STEM WALL/RETAINING WALL | DQUINN | Approved | FOOTING FOR GARBAGE ENCLOSURE- OK |
04/29/2013 | STEM WALL/RETAINING WALL | DQUINN | Approved | IVRS - Inspection :* |
05/03/2013 | PLUMBING - ROUGH, SOIL | AQUIROZ | Approved | IVRS - Inspection :* |
05/20/2013 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
05/24/2013 | ELECTRIC - UNDERGROUND | DQUINN | Approved | LIGHT POLE CONDUIT OK TO BURY |
05/24/2013 | ELECTRIC - UNDERGROUND | DQUINN | Approved | IVRS - Inspection :* |
08/06/2013 | PLUMBING - GAS PRESSURE TEST | MPUGH | Approved | IVRS - Inspection :* |
08/06/2013 | FRAMING | MPUGH | Approved | IVRS - Inspection :* |
08/06/2013 | ROOF NAILING | MPUGH | Approved | IVRS - Inspection :* |
08/07/2013 | PLUMBING - INTERMEDIATE | MPUGH | Approved | IVRS - Inspection :* |
08/07/2013 | PLUMBING - ROOF DRAINS | MPUGH | Approved | IVRS - Inspection :* |
08/15/2013 | STUCCO MESH | MPUGH | Approved | IVRS - Inspection :* |
08/22/2013 | MECHANICAL - INTERMEDIATE | MPUGH | Approved | IVRS - Inspection :* |
08/27/2013 | FIRE SPKLR - OH PIPING & HYDRO | wmotto | Approved | |
08/27/2013 | FIRE SPKLR - UG PIPING FLUSH | wmotto | Approved | |
08/29/2013 | SHEET ROCK NAILING | MPUGH | Approved | IVRS - Inspection :* |
10/10/2013 | TEP CLEARANCE - AM | MPUGH | Approved | TEC |
10/21/2013 | MECHANICAL - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
10/21/2013 | ELECTRIC - OUTDOOR LIGHTING | MPUGH | Approved | IVRS - Inspection :* |
10/21/2013 | ELECTRIC - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
11/13/2013 | FIRE - ALARM FINAL | CBASALDU | Approved | |
11/13/2013 | FIRE SPKLR - FINAL | CBASALDU | Approved | |
11/13/2013 | PLUMBING - PRE SLAB | MPUGH | Approved | |
11/13/2013 | PLUMBING - ABOVE CEILING | MPUGH | Approved | |
11/13/2013 | PLUMBING - YARD WTR LINE/TEST | MPUGH | Approved | |
11/13/2013 | PLUMBING - PROGRESS | MPUGH | Approved | |
11/13/2013 | ELECTRIC - INTERMEDIATE | MPUGH | Approved | |
11/13/2013 | ELECTRIC - PROGRESS | MPUGH | Approved | |
11/13/2013 | ELECTRIC - FINAL | MPUGH | Approved | OK FOR STOCKING & TRAINING |
11/13/2013 | RIGHT OF WAY - FINAL | TW | Approved | |
11/13/2013 | MECHANICAL - FINAL | MPUGH | Approved | IVRS - Inspection :* |
11/13/2013 | PLUMBING - FINAL | MPUGH | Approved | IVRS - Inspection :* |
11/13/2013 | ELECTRIC - FINAL | MPUGH | Approved | IVRS - Inspection :* |
11/13/2013 | U VALUE FOR WINDOW | MPUGH | Approved | IVRS - Inspection :* |
11/14/2013 | NPPO - FINAL | MRUSSO | Approved | |
11/14/2013 | SIGN - FINAL | MRUSSO | Approved | |
11/18/2013 | BUILDING - FINAL | MPUGH | Approved | PENDING FIRE FINAL |
11/18/2013 | BUILDING - FINAL | MPUGH | Approved | IVRS - Inspection :* |
11/18/2013 | BUILDING - PROGRESS | MPUGH | Approved | IVRS - Inspection :* |
11/18/2013 | BUILDING ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
11/18/2013 | EXT METAL CLIPS/EXT SHEATHING | MPUGH | Approved | IVRS - Inspection :* |
11/18/2013 | REINFORCED MASONRY PRE-GROUT | MPUGH | Approved | IVRS - Inspection :* |
11/18/2013 | EXCAVATION/LAYOUT REBAR & ZON | MPUGH | Approved | IVRS - Inspection :* |
11/19/2013 | FIRE - FINAL | CBASALDU | Approved | |
11/19/2013 | LANDSCAPE - FINAL | MRUSSO | Approved | |
11/19/2013 | ENGINEERING - FINAL | MRUSSO | Approved |