Permit: T12CM07075
Permit Details
Apply Date:
11/06/2012
Applicant:
KYLE BOYD DESIGN AND CONSTRUCTION
Description:
BATHROOM & CLOSET ADDITION & CARPORT/STORAGE & PERMIT TWO (2) SHEDS 120 SF OR UNDER.
Contractors:
- KYLE BOYD DESIGN AND CONSTRUCTION
Permit Reviews
Permit Number - T12CM07075
Permit Status: Final
Permit Description: BATHROOM & CLOSET ADDITION & CARPORT/STORAGE & PERMIT TWO (2) SHEDS 120 SF OR UNDER.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/06/2012 | RESIDENTIAL - BLDG/ZONING/ENGINE/WWM | 11/06/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM07075
Permit Status: Final
Permit Description: BATHROOM & CLOSET ADDITION & CARPORT/STORAGE & PERMIT TWO (2) SHEDS 120 SF OR UNDER.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/06/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T12CM07075
Permit Description: BATHROOM & CLOSET ADDITION & CARPORT/STORAGE & PERMIT TWO (2) SHEDS 120 SF OR UNDER.
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/09/2012 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | |
| 11/09/2012 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | |
| 11/29/2012 | U VALUE FOR WINDOW | DWALKER | Approved | IVRS - Inspection :* |
| 11/29/2012 | ROOF NAILING | DWALKER | Approved | IVRS - Inspection :* |
| 12/07/2012 | FRAMING | DWALKER | Approved | IVRS - Inspection :* |
| 12/07/2012 | MECHANICAL - INTERMEDIATE | DWALKER | Approved | IVRS - Inspection :* |
| 12/07/2012 | PLUMBING - INTERMEDIATE | DWALKER | Approved | IVRS - Inspection :* |
| 12/07/2012 | ELECTRIC - INTERMEDIATE | DWALKER | Approved | IVRS - Inspection :* |
| 12/13/2012 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/19/2013 | MECHANICAL - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/19/2013 | PLUMBING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/19/2013 | ELECTRIC - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/19/2013 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/19/2013 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/19/2013 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |