Permit: T12CM06995
Permit Details
Apply Date:
11/01/2012
Applicant:
SONORAN DESIGN GROUP
Description:
NEW SFR
Permit Reviews
Permit Number - T12CM06995
Permit Status: C of o
Permit Description: NEW SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/30/2013 | REVISION - - 1ST | 05/02/2013 | COMPLETED |
| 11/01/2012 | PLANS OK TO SUBMIT - RES | 11/01/2012 | COMPLETED |
| 11/01/2012 | RESIDENTIAL - BLDG/WWM | 12/10/2012 | COMPLETED |
| 12/10/2012 | RESUBMITTAL | 04/15/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM06995
Permit Status: C of o
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/01/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM06995
Permit Description: NEW SFR
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/02/2013 | PLUMBING - ROUGH, SOIL | JMILITEL | Approved | IVRS - Inspection :* |
| 05/03/2013 | ELECTRIC - UNDERGROUND | DQUINN | Approved | IVRS - Inspection :* |
| 05/03/2013 | ELECTRIC - UFER | DQUINN | Approved | IVRS - Inspection :* |
| 05/03/2013 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
| 05/03/2013 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | IVRS - Inspection :* |
| 05/14/2013 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 05/14/2013 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | IVRS - Inspection :* |
| 05/16/2013 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | IVRS - Inspection :* |
| 06/12/2013 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | |
| 06/13/2013 | MECHANICAL - INTERMEDIATE | DQuinn | Approved | |
| 06/13/2013 | PLUMBING - INTERMEDIATE | DQuinn | Approved | |
| 06/13/2013 | ELECTRIC - INTERMEDIATE | DQuinn | Approved | |
| 06/13/2013 | U VALUE FOR WINDOW | DQuinn | Approved | |
| 06/13/2013 | STUCCO MESH | DQuinn | Approved | |
| 06/13/2013 | FRAMING | DQuinn | Approved | |
| 06/21/2013 | ELECTRIC - CONSTRUCTION POWER | dquinn | Approved | |
| 06/21/2013 | ELECTRIC - CABLE DROP | dquinn | Approved | |
| 06/21/2013 | SHEET ROCK NAILING | dquinn | Approved | |
| 06/24/2013 | TEP CLEARANCE - AM | DQUINN | Approved | ECO |
| 08/02/2013 | MECHANICAL - FINAL | dquinn | Approved | |
| 08/02/2013 | PLUMBING - FINAL | dquinn | Approved | |
| 08/02/2013 | PLUMBING - GAS PRESSURE TEST | dquinn | Approved | |
| 08/02/2013 | OUTDOOR LIGHTING FINAL | dquinn | Approved | |
| 08/02/2013 | ELECTRIC - FINAL | dquinn | Approved | |
| 08/02/2013 | BUILDING - FINAL | dquinn | Approved |