Permit: T12CM06950
Permit Details
Apply Date:
10/31/2012
Applicant:
INNOVATIVE DESIGN & CONSTRUCTION LLC
Description:
REPAIR:CAR DAMAGE INTO BLDG:T12DV09844
Contractors:
- INNOVATIVE DESIGN & CONSTRUCTION LLC
Permit Reviews
Permit Number - T12CM06950
Permit Status: Final
Permit Description: REPAIR:CAR DAMAGE INTO BLDG:T12DV09844
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/31/2012 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 10/31/2012 | COMPLETED |
| 11/07/2012 | REVISION - - 1ST | 11/08/2012 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T12CM06950
Permit Description: REPAIR:CAR DAMAGE INTO BLDG:T12DV09844
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/15/2012 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | IVRS - Inspection :* |
| 11/29/2012 | PLUMBING - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
| 11/29/2012 | PLUMBING - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 09/11/2013 | FIRE - FINAL | CBASALDU | Approved | |
| 09/11/2013 | BUILDING - FINAL | RCAMACHO | Approved | 1. PROVIDE COMBUSTER RELIEF PER PLAN 2. CONDENSATE LINES TO EXISTING TO EXISTING FLOOR SINK. SINK DOES NOT DRAIN 3. PROVIDE SPECIAL INSP REPORTS 4. SECURE ALL PLUMBING TO CODE 5. ELECTRICAL NOT TO CODE/OPEN BOXES, OPEN CONDUCTORS THROUGHOUT/ FLEX MC CABLE 110 WH CONNECTION 6. COMPLY WITH NOTE 12 PLUMB NOTES 7. LEAK @ FITTING UNDERGROUND MAIN - STOPPED INSPECTION |
| 09/11/2013 | PLUMBING - GAS PRESSURE TEST | RCAMACHO | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 09/11/2013 | PLUMBING - FINAL | RCAMACHO | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 09/11/2013 | ELECTRIC - FINAL | RCAMACHO | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 09/11/2013 | BUILDING - FINAL | RCAMACHO | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 09/12/2013 | RIGHT OF WAY - FINAL | TW | Approved | |
| 09/12/2013 | NPPO - FINAL | RLEDONNE | Approved | |
| 09/12/2013 | SIGN - FINAL | RLEDONNE | Approved | |
| 09/12/2013 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 09/12/2013 | ENGINEERING - FINAL | RLEDONNE | Approved |