Permit: T12CM06869
Permit Details
Apply Date:
10/29/2012
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: MEDICAL OFFICE
Contractors:
- D P R CONSTRUCTION INC ,
Permit Reviews
Permit Number - T12CM06869
Permit Status: Final
Permit Description: TI: MEDICAL OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/29/2012 | PLANS OK TO SUBMIT - COMM | 10/29/2012 | COMPLETED |
10/29/2012 | COMMERCIAL - TI | 11/21/2012 | COMPLETED |
11/21/2012 | RESUBMITTAL - TI ALL | 12/06/2012 | COMPLETED |
12/06/2012 | RESUBMITTAL | 12/10/2012 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T12CM06869
Permit Status: Final
Permit Description: TI: MEDICAL OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/29/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T12CM06869
Permit Description: TI: MEDICAL OFFICE
Total Completed Inspections - 29
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/12/2012 | BUILDING - PROGRESS | BBENEDON | Approved | SUITE 151 |
12/14/2012 | PLUMBING - ROUGH, SOIL | JMILITEL | Approved | IVRS - Inspection :* |
12/19/2012 | PLUMBING - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* TEST OK ON 3 NEW RISERS TO UPSTAIR BATHROOMS AND KITCHEN SINK |
12/19/2012 | PLUMBING - PRE SLAB | JMILITEL | Approved | IVRS - Inspection :* |
12/19/2012 | ELECTRIC - UNDERGROUND | JMILITEL | Approved | IVRS - Inspection :* |
01/23/2013 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
01/31/2013 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* |
01/31/2013 | ELECTRIC - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
02/15/2013 | SHEET ROCK NAILING | JMILITEL | Approved | IVRS - Inspection :* DO NOT USE SHEET ROCK SCREWS TO SECURE TBAR TO WALL |
03/11/2013 | PLUMBING - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
04/02/2013 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
04/02/2013 | ELECTRIC - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
04/02/2013 | BUILDING ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
04/12/2013 | NPPO - FINAL | RLEDONNE | Approved | |
04/12/2013 | SIGN - FINAL | RLEDONNE | Approved | |
04/12/2013 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
04/12/2013 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
04/15/2013 | MECHANICAL - HOODS | RHOLLAND | Approved | PER BU FINAL |
04/15/2013 | MECHANICAL - INTERMEDIATE | RHOLLAND | Approved | PER BU FINAL |
04/15/2013 | MECHANICAL - FINAL | RHOLLAND | Approved | RECEIVED REPORTS- CLORINATION, BACKWATER AND AIR BALANCE. |
04/15/2013 | MECHANICAL - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
04/15/2013 | PLUMBING - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
04/16/2013 | FRAMING | RMORENO | Approved | PER BU FINAL |
04/16/2013 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
04/16/2013 | BUILDING - FINAL | RMORENO | Approved | IVRS - Inspection :* |
04/18/2013 | FIRE - FINAL | WMOTTO | Approved | |
04/18/2013 | FIRE - ALARM FINAL | WMOTTO | Approved | |
04/18/2013 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
04/19/2013 | ENGINEERING - FINAL | MRUSSO | Approved |