Permit: T12CM06416
Permit Details
Apply Date:
10/12/2012
Applicant:
ALLEN SWANSON
Description:
DEMOLITION OF TEMPORARY BUILDING AND CARPORT. NEW CONSTRUCTION OF WORKSHOP AND GARAGE
Architects:
- EDWARD A. VERGARA
Permit Reviews
Permit Number - T12CM06416
Permit Status: Final
Permit Description: DEMOLITION OF TEMPORARY BUILDING AND CARPORT. NEW CONSTRUCTION OF WORKSHOP AND GARAGE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/12/2012 | RESIDENTIAL - BLDG/ZONING/ENGINE/WWM | 10/15/2012 | COMPLETED |
10/15/2012 | RESIDENTIAL - BLDG/WWM | 11/13/2012 | COMPLETED |
11/19/2012 | RESUBMITTAL | 11/19/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM06416
Permit Status: Final
Permit Description: DEMOLITION OF TEMPORARY BUILDING AND CARPORT. NEW CONSTRUCTION OF WORKSHOP AND GARAGE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/12/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T12CM06416
Permit Description: DEMOLITION OF TEMPORARY BUILDING AND CARPORT. NEW CONSTRUCTION OF WORKSHOP AND GARAGE
Total Completed Inspections - 17
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/15/2013 | ELECTRIC - UNDERGROUND | RMYERS | Approved | |
01/18/2013 | ELECTRIC - UFER | AQUIROZ | Approved | IVRS - Inspection :* |
01/18/2013 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
01/18/2013 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |
01/18/2013 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | |
02/21/2013 | REINFORCED MASONRY PRE-GROUT | RMYERS | Approved | |
06/05/2013 | PLUMBING - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
06/05/2013 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
06/05/2013 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
09/27/2013 | ELECTRIC - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
12/27/2013 | MECHANICAL - INTERMEDIATE | MPUGH | Approved | PER MECH FINAL - MPUGH |
12/27/2013 | PLUMBING - YARD WTR LINE/TEST | MPUGH | Approved | PER PLMB FINAL - MPUGH |
12/27/2013 | PLUMBING - SEWER HCS CONNECT | MPUGH | Approved | PER PLMB FINAL - MPUGH |
12/27/2013 | MECHANICAL - FINAL | MPUGH | Approved | IVRS - Inspection :* |
12/27/2013 | PLUMBING - FINAL | MPUGH | Approved | IVRS - Inspection :* |
12/27/2013 | ELECTRIC - FINAL | MPUGH | Approved | IVRS - Inspection :* |
12/27/2013 | BUILDING - FINAL | MPUGH | Approved | IVRS - Inspection :* |