Permit Details

Status:
Expired
Type:
COMMERCIAL ADDITION
Address:
350 N WILMOT RD
Address NEW:
350 N WILMOT RD
Apply Date:
08/08/2012
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW CHAPEL AT ST JOSEPH'S HOSPITAL
Architects:
  • BOLLARD, MARK EDWARD
Contractors:
  • W. E. O'NEIL

Permit Reviews

Permit Number - T12CM04879
Permit Status: Expired
Permit Description: NEW CHAPEL AT ST JOSEPH'S HOSPITAL
Start Date Submittal Complete Date Status  
08/08/2012 PLANS OK TO SUBMIT - COMM 08/08/2012 COMPLETED Review Details
08/08/2012 COMMERCIAL - TI 09/05/2012 COMPLETED Review Details
09/05/2012 RESUBMITTAL 10/15/2012 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T12CM04879
Permit Status: Expired
Permit Description: NEW CHAPEL AT ST JOSEPH'S HOSPITAL
Total Outstanding Activity Conditions - 7
Date Name
08/08/2012 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
08/16/2012 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
08/16/2012 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
08/16/2012 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
08/16/2012 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
08/16/2012 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
08/16/2012 SPECIAL INSPECTION IS REQUIRED FOR FRP INSTALLATION

Completed Inspections

Permit Status: Expired
Permit Number: T12CM04879
Permit Description: NEW CHAPEL AT ST JOSEPH'S HOSPITAL
Total Completed Inspections - 35
Date Description Inspector Results Comments
10/26/2012 PLUMBING - ROUGH, SOIL JMILITEL Approved IVRS - Inspection :*
11/08/2012 ELECTRIC - INTERMEDIATE JMILITEL Approved OK TO COVER ELEC. CONDUITS IN TRENCH. OK TO POUR 5 POST FOOTINGS.
11/30/2012 BUILDING PRE-SLAB RHOLLAND Approved IVRS - Inspection :*
12/17/2012 PLUMBING - ROOF DRAINS JMILITEL Approved IVRS - Inspection :*
12/27/2012 EXCAVATION/LAYOUT REBAR & ZON JMILITEL Approved IVRS - Inspection :* CHECKED FOOTINGS FOR 5 REMAINING SCREEN AND SEAT WALLS. OK TO POUR AND TOP OFF.
01/23/2013 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved IVRS - Inspection :*
01/28/2013 PLUMBING - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
02/04/2013 MECHANICAL - HYDRONIC PIPING JMILITEL Approved IVRS - Inspection :*OK TO INSULATE CHILLED AND HOT WATER LINES TO A/C UNIT. EXTEND VENT ON CONDENSATE DRAIN TRAP.
02/12/2013 RIGHT OF WAY - FINAL P.Whiddon Approved
03/15/2013 SHEET ROCK NAILING JMILITEL Approved IVRS - Inspection :*
03/26/2013 PLUMBING - ABOVE CEILING JBURGE Approved IVRS - Inspection :*
03/26/2013 ELECTRIC - ABOVE CEILING JBURGE Approved IVRS - Inspection :*
04/12/2013 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
04/12/2013 PLUMBING - FINAL JMILITEL Approved IVRS - Inspection :*
04/12/2013 PLUMBING - PROGRESS JMILITEL Approved IVRS - Inspection :*
04/12/2013 PLUMBING - SEWER HCS CONNECT JMILITEL Approved IVRS - Inspection :*
04/12/2013 ELECTRIC - FINAL JMILITEL Approved IVRS - Inspection :*
04/12/2013 U VALUE FOR WINDOW JMILITEL Approved IVRS - Inspection :*
04/12/2013 STUCCO MESH JMILITEL Approved IVRS - Inspection :*
04/12/2013 BUILDING ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
04/12/2013 FRAMING JMILITEL Approved IVRS - Inspection :*
04/12/2013 FIRE - FINAL WMOTTO Approved
04/12/2013 FIRE - ALARM FINAL WMOTTO Approved
04/12/2013 FIRE SPKLR - FINAL WMOTTO Approved
04/12/2013 NPPO - FINAL RLEDONNE Approved
04/12/2013 SIGN - FINAL RLEDONNE Approved
04/18/2013 MECHANICAL - FINAL JMILITEL Approved NEED TO TEST DUCT SMOKE DETECTOR. AIR BALANCE OK BACKFLOW TEST OK STERILIZATION OK
04/18/2013 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
04/19/2013 BUILDING - FINAL RHOLLAND Approved IVRS - Inspection :*
04/22/2013 LANDSCAPE - FINAL MRUSSO Approved
04/22/2013 ENGINEERING - FINAL MRUSSO Approved
04/23/2013 MECHANICAL - INTERMEDIATE JMILITEL Approved PER FINAL
04/23/2013 BUILDING - PROGRESS RHOLLAND Approved PER BU FINAL
04/23/2013 FIREWALL/FIREBARRIER/FIRESTOP RHOLLAND Approved PER BU FINAL
04/23/2013 STEM WALL/RETAINING WALL RHOLLAND Approved PER BU FINAL