Permit: T12CM04619
Permit Details
Apply Date:
07/30/2012
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
CAR DEALERSHIP TCO FOR STOCKING ONLY
Architects:
- ACORN, KIM BRIAN
Contractors:
- CANYON BUILDING AND DESIGN LLC *APA*
Permit Reviews
Permit Number - T12CM04619
Permit Status: C of o
Permit Description: CAR DEALERSHIP TCO FOR STOCKING ONLY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/14/2013 | REVISION - - 2ND | 02/14/2013 | ACTIVE |
| 07/30/2012 | PLANS OK TO SUBMIT - COMM | 07/30/2012 | COMPLETED |
| 07/30/2012 | COMMERCIAL - TI | 09/06/2012 | COMPLETED |
| 09/06/2012 | RESUBMITTAL - TI ALL | 10/04/2012 | COMPLETED |
| 10/04/2012 | RESUBMITTAL | 10/16/2012 | COMPLETED |
| 11/06/2012 | REVISION - - 1ST | 02/13/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM04619
Permit Status: C of o
Permit Description: CAR DEALERSHIP TCO FOR STOCKING ONLY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/30/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM04619
Permit Description: CAR DEALERSHIP TCO FOR STOCKING ONLY
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/29/2012 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 10/29/2012 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 10/30/2012 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | OFFICES CONFERENCE ROOM BREAK ROOM |
| 10/30/2012 | FRAMING | JBURGE | Approved | OFFICES AND CONFERENCE ROOM, BREAK ROOM |
| 11/06/2012 | SHEET ROCK NAILING | JBURGE | Approved | OFFICES AND RESTROOM AREAS (SW AREA) OK TO TAPE PROGRESS AREAS. |
| 11/14/2012 | ELECTRIC - UNDERGROUND | JBURGE | Approved | IVRS - Inspection :* |
| 11/19/2012 | PLUMBING - PROGRESS | JBURGE | Approved | RESTROOMS OK TO COVER |
| 12/05/2012 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :*OFFICE AREAS-OK TO INSULATE PROGRESS AREAS |
| 12/18/2012 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* |
| 12/28/2012 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* |
| 12/28/2012 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* |
| 01/31/2013 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 01/31/2013 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 01/31/2013 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* |
| 03/01/2013 | FIRE - FINAL | WMOTTO | Approved | |
| 03/01/2013 | MECHANICAL - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 03/01/2013 | PLUMBING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 03/01/2013 | ELECTRIC - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 03/01/2013 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 03/01/2013 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 03/01/2013 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 03/01/2013 | FIREWALL/FIREBARRIER/FIRESTOP | JBURGE | Approved | IVRS - Inspection :* |
| 03/01/2013 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
| 03/01/2013 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 03/04/2013 | NPPO - FINAL | MRUSSO | Approved | |
| 03/04/2013 | SIGN - FINAL | MRUSSO | Approved | |
| 03/04/2013 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 03/04/2013 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 03/05/2013 | RIGHT OF WAY - FINAL | P.Whiddon | Approved |