Permit: T12CM04064
Permit Details
Apply Date:
07/09/2012
Applicant:
DANA HOLGUIN
Description:
TI/ADDITION: OFFICE, PARTIAL DEMO/REMODEL FACADE
Architects:
- GARCIA DAVID V
Contractors:
- MEGA TREND INC ,
Permit Reviews
Permit Number - T12CM04064
Permit Status: Expired
Permit Description: TI/ADDITION: OFFICE, PARTIAL DEMO/REMODEL FACADE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/09/2012 | PLANS OK TO SUBMIT - COMM | 07/10/2012 | COMPLETED |
07/10/2012 | COMMERCIAL - TI | 08/14/2012 | COMPLETED |
08/14/2012 | RESUBMITTAL | 08/14/2012 | COMPLETED |
08/14/2012 | RESUBMITTAL | 08/23/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM04064
Permit Status: Expired
Permit Description: TI/ADDITION: OFFICE, PARTIAL DEMO/REMODEL FACADE
Total Outstanding Activity Conditions - 10
Date | Name |
---|---|
07/09/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
07/20/2012 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
07/20/2012 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
07/20/2012 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
07/20/2012 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. |
07/20/2012 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
07/20/2012 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
07/20/2012 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
07/20/2012 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
07/20/2012 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
Completed Inspections
Permit Status: Expired
Permit Number: T12CM04064
Permit Description: TI/ADDITION: OFFICE, PARTIAL DEMO/REMODEL FACADE
Total Completed Inspections - 29
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/06/2012 | BUILDING PRE-SLAB | JMILITEL | Approved | IVRS - Inspection :* |
09/24/2012 | ROOF NAILING | JMILITEL | Approved | IVRS - Inspection :* |
09/26/2012 | EXT METAL CLIPS/EXT SHEATHING | JMILITEL | Approved | IVRS - Inspection :* |
10/04/2012 | FRAMING | DWALKER | Approved | IVRS - Inspection :* |
10/04/2012 | MECHANICAL - INTERMEDIATE | DWALKER | Approved | IVRS - Inspection :* |
10/04/2012 | PLUMBING - INTERMEDIATE | DWALKER | Approved | IVRS - Inspection :* |
10/04/2012 | ELECTRIC - INTERMEDIATE | DWALKER | Approved | IVRS - Inspection :* |
10/04/2012 | MECHANICAL - ABOVE CEILING | DWALKER | Approved | IVRS - Inspection :* |
10/04/2012 | U VALUE FOR WINDOW | DWALKER | Approved | IVRS - Inspection :* |
10/04/2012 | BUILDING ABOVE CEILING | DWALKER | Approved | IVRS - Inspection :* |
10/04/2012 | BUILDING - PROGRESS | DWALKER | Approved | IVRS - Inspection :* |
10/04/2012 | ELECTRIC - ABOVE CEILING | DWALKER | Approved | IVRS - Inspection :* |
10/04/2012 | PLUMBING - ABOVE CEILING | DWALKER | Approved | IVRS - Inspection :* |
10/04/2012 | PLUMBING - PRE SLAB | DWALKER | Approved | IVRS - Inspection :* |
10/04/2012 | PLUMBING - PROGRESS | DWALKER | Approved | IVRS - Inspection :* |
10/04/2012 | PLUMBING - ROUGH, SOIL | DWALKER | Approved | IVRS - Inspection :* |
10/09/2012 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
10/09/2012 | STUCCO MESH | DQUINN | Approved | IVRS - Inspection :* |
10/09/2012 | STEM WALL/RETAINING WALL | DQUINN | Approved | IVRS - Inspection :* |
10/19/2012 | EXCAVATION/LAYOUT REBAR & ZON | JMILITEL | Approved | IVRS - Inspection :* |
11/07/2012 | PLUMBING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
11/07/2012 | ELECTRIC - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
11/07/2012 | FIRE - FINAL | CSCHULTZ | Approved | |
11/13/2012 | RIGHT OF WAY - FINAL | TWOLFGAN | Approved | |
11/13/2012 | MECHANICAL - FINAL | RMYERS | Approved | IVRS - Inspection :* |
11/13/2012 | BUILDING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
11/19/2012 | NPPO - FINAL | RLEDONNE | Approved | |
11/20/2012 | SIGN - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
11/21/2012 | LANDSCAPE - FINAL | RLEDONNE | Approved |