Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T12CM03721
Permit Details
Apply Date:
06/22/2012
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
CANOPY FOR NEW QUIKTRIP
Contractors:
- M T V GENERAL CONTRACTORS INC ,
Permit Reviews
Permit Number - T12CM03721
Permit Status: Final
Permit Description: CANOPY FOR NEW QUIKTRIP
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/22/2012 | PLANS OK TO SUBMIT - COMM | 06/22/2012 | COMPLETED |
06/22/2012 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/10/2012 | COMPLETED |
08/10/2012 | RESUBMITTAL | 09/18/2012 | COMPLETED |
09/19/2012 | RESUBMITTAL | 10/08/2012 | COMPLETED |
10/08/2012 | RESUBMITTAL | 10/22/2012 | COMPLETED |
10/22/2012 | RESUBMITTAL | 11/05/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM03721
Permit Status: Final
Permit Description: CANOPY FOR NEW QUIKTRIP
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/22/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T12CM03721
Permit Description: CANOPY FOR NEW QUIKTRIP
Total Completed Inspections - 18
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/06/2012 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | 2 @ 20' CAISSON FOOTINGS- OK TO POUR PROGRESS AREAS |
12/06/2012 | ELECTRIC - UNDERGROUND | JBURGE | Approved | 1" conduit lines for pumps/lighting ok to cover |
12/12/2012 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | PARTIAL 16 COLUMNS- CMU AT 4' AFFE. OK TO GROUT PROGRESS AREAS |
01/11/2013 | PLUMBING - ROOF DRAINS | JBURGE | Approved | IVRS - Inspection :* |
02/12/2013 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* |
02/12/2013 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* |
02/25/2013 | TEP CLEARANCE - AM | JBURGE | Approved | |
02/25/2013 | ELECTRIC - FINAL | JBURGE | Approved | IVRS - Inspection :* |
02/28/2013 | FIRE - FINAL | CFUNKE | Approved | |
03/01/2013 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | |
03/01/2013 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
03/04/2013 | NPPO - FINAL | MRUSSO | Approved | |
03/04/2013 | SIGN - FINAL | MRUSSO | Approved | |
03/04/2013 | LANDSCAPE - FINAL | MRUSSO | Approved | |
03/04/2013 | ENGINEERING - FINAL | MRUSSO | Approved | |
03/05/2013 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
03/07/2013 | PLUMBING - INTERMEDIATE | JBURGE | Approved | |
03/08/2013 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |