Permit: T12CM03226
Permit Details
Apply Date:
06/05/2012
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW SOFTBALL BUILDING FOR SALPOINT HIGH SCHOOL
Architects:
- FRANKS, MICHAEL WILLIAM
Contractors:
- DIVERSIFIED DESIGN AND CONSTRUCT
Permit Reviews
Permit Number - T12CM03226
Permit Status: C of o
Permit Description: NEW SOFTBALL BUILDING FOR SALPOINT HIGH SCHOOL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/05/2012 | COMMERCIAL - NEW | 06/08/2012 | COMPLETED |
| 06/08/2012 | COMMERCIAL - NEW | 07/17/2012 | COMPLETED |
| 07/19/2012 | RESUBMITTAL | 08/20/2012 | COMPLETED |
| 08/20/2012 | RESUBMITTAL | 08/22/2012 | COMPLETED |
| 11/06/2012 | REVISION - - 1ST | 11/09/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM03226
Permit Status: C of o
Permit Description: NEW SOFTBALL BUILDING FOR SALPOINT HIGH SCHOOL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/05/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM03226
Permit Description: NEW SOFTBALL BUILDING FOR SALPOINT HIGH SCHOOL
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/12/2012 | PLUMBING - ROUGH, SOIL | MPUGH | Approved | IVRS - Inspection :* |
| 09/18/2012 | PLUMBING - YARD WTR LINE/TEST | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/18/2012 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/20/2012 | REINFORCED MASONRY PRE-GROUT | DSANTACR | Approved | 1ST LIFTDUGOUTS AND COLUMNS |
| 09/21/2012 | SITE - SEWER | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/04/2012 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/11/2012 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/11/2012 | PLUMBING - PRE SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/11/2012 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/24/2012 | PLUMBING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/15/2012 | PLUMBING - ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/15/2012 | PLUMBING - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/15/2012 | ELECTRIC - ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/15/2012 | ELECTRIC - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
| 01/23/2013 | RIGHT OF WAY - FINAL | TWOLFGAN | Approved | |
| 01/23/2013 | FIRE - FINAL | CBASALDU | Approved | |
| 01/23/2013 | ELECTRIC - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 01/24/2013 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 01/24/2013 | NPPO - FINAL | MRUSSO | Approved | |
| 01/24/2013 | SIGN - FINAL | MRUSSO | Approved | |
| 01/24/2013 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 01/24/2013 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 01/25/2013 | PLUMBING - FINAL | AQUIROZ | Approved | |
| 01/25/2013 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | PER BUILD. FINAL |