Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T12CM02496
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
2800 N CAMPBELL AV #110
Address NEW:
2800 N CAMPBELL AV #110
Apply Date:
05/07/2012
Applicant:
HENGST, KEVIN P
Description:
TI: YOGURT LAND
Architects:
- HENGST, KEVIN P
Contractors:
- M C O AND ASSOCIATES L L C
Permit Reviews
Permit Number - T12CM02496
Permit Status: C of o
Permit Description: TI: YOGURT LAND
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/07/2012 | PLANS OK TO SUBMIT - COMM | 05/07/2012 | COMPLETED |
| 05/07/2012 | COMMERCIAL - TI | 07/25/2012 | COMPLETED |
| 07/25/2012 | RESUBMITTAL - TI ALL | 07/31/2012 | COMPLETED |
| 07/31/2012 | RESUBMITTAL - TI ALL | 09/06/2012 | COMPLETED |
| 09/06/2012 | RESUBMITTAL | 09/21/2012 | COMPLETED |
| 09/21/2012 | RESUBMITTAL | 09/26/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM02496
Permit Status: C of o
Permit Description: TI: YOGURT LAND
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/07/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM02496
Permit Description: TI: YOGURT LAND
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/16/2012 | PLUMBING - ROUGH, SOIL | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/18/2012 | PLUMBING - PRE SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/06/2012 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/09/2012 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | |
| 11/09/2012 | STUCCO MESH | DWALKER | Approved | IVRS - Inspection :* |
| 11/13/2012 | PLUMBING - INTERMEDIATE | DWALKER | Approved | IVRS - Inspection :* |
| 11/13/2012 | MECHANICAL - INTERMEDIATE | DWALKER | Approved | IVRS - Inspection :* |
| 11/13/2012 | ELECTRIC - INTERMEDIATE | DWALKER | Approved | IVRS - Inspection :* |
| 11/13/2012 | FIREWALL/FIREBARRIER/FIRESTOP | DWALKER | Approved | IVRS - Inspection :* |
| 11/13/2012 | FRAMING | DWALKER | Approved | IVRS - Inspection :* |
| 11/21/2012 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/13/2012 | ELECTRIC - SERVICE UPGRADE | DWALKER | Approved | IVRS - Inspection :* UNIT HAS POWER- CONTRACTOR TO INSTALL OUTER METER E-MON D-MON BEFORE FINAL INSPECTIONS |
| 12/14/2012 | MECHANICAL - ABOVE CEILING | DWALKER | Approved | IVRS - Inspection :* |
| 12/14/2012 | PLUMBING - ABOVE CEILING | DWALKER | Approved | IVRS - Inspection :* |
| 12/14/2012 | ELECTRIC - ABOVE CEILING | DWALKER | Approved | IVRS - Inspection :* |
| 12/14/2012 | BUILDING ABOVE CEILING | DWALKER | Approved | IVRS - Inspection :* |
| 01/28/2013 | ELECTRIC - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/01/2013 | FIRE - FINAL | CBASALDU | Approved | |
| 02/01/2013 | FIRE SPKLR - FINAL | CBASALDU | Approved | |
| 02/04/2013 | RIGHT OF WAY - FINAL | TWOLFGAN | Approved | |
| 02/04/2013 | NPPO - FINAL | RLEDONNE | Approved | NA TOTHIS ACTIVITY. |
| 02/04/2013 | SIGN - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
| 02/04/2013 | LANDSCAPE - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
| 02/07/2013 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 02/08/2013 | PLUMBING - PROGRESS | AQUIROZ | Approved | |
| 02/08/2013 | HEALTH DEPT - FINAL 724-7908 | WARREN | Approved | |
| 02/08/2013 | MECHANICAL - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/08/2013 | PLUMBING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/08/2013 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |