Permit: T12CM02063
Permit Details
Apply Date:
04/19/2012
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
STUDENT HOUSING
Contractors:
- SUMMIT BUILDERS ,
Permit Reviews
Permit Number - T12CM02063
Permit Status: C of o
Permit Description: STUDENT HOUSING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/19/2012 | PLANS OK TO SUBMIT - COMM | 04/19/2012 | COMPLETED |
04/19/2012 | COMMERCIAL - NEW | 06/26/2012 | COMPLETED |
06/13/2012 | RESUBMITTAL | 07/31/2012 | COMPLETED |
07/31/2012 | RESUBMITTAL | 08/30/2012 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM02063
Permit Description: STUDENT HOUSING
Total Completed Inspections - 46
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/19/2012 | PLUMBING - PRE SLAB | LHANLY | Approved | |
11/19/2012 | PLUMBING - ROUGH, SOIL | LHANLY | Approved | |
11/19/2012 | ROOF NAILING | LHANLY | Approved | |
11/19/2012 | BUILDING PRE-SLAB | LHANLY | Approved | OK TO PLACE GYP-CRETE AT TUBS AND VOIDS |
11/19/2012 | STEM WALL/RETAINING WALL | LHANLY | Approved | |
11/19/2012 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | |
12/12/2012 | FRAMING | LHANLY | Approved | |
12/14/2012 | PLUMBING - PROGRESS | LHANLY | Approved | |
12/14/2012 | PLUMBING - ABOVE CEILING | LHANLY | Approved | |
12/14/2012 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | COURTYARD LEVEL 5 ALL AROUND COURTYARD LEVEL 6 E,S,N ONLY COURTYARD LEVEL 7 E ONLY |
12/14/2012 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | PROGRESS TO LEVEL 7 OK |
12/24/2012 | PLUMBING - INTERMEDIATE | RMYERS | Approved | 1. 6th and 7th floor PVC DWV in walls and overhead. |
03/12/2013 | U VALUE FOR WINDOW | LHANLY | Approved | |
03/12/2013 | STUCCO MESH | LHANLY | Approved | |
03/12/2013 | BUILDING ABOVE CEILING | LHANLY | Approved | |
05/06/2013 | PLUMBING - YARD WTR LINE/TEST | LHANLY | Approved | |
05/06/2013 | PLUMBING - ROOF DRAINS | LHANLY | Approved | |
05/06/2013 | MECHANICAL - INTERMEDIATE | LHANLY | Approved | |
05/29/2013 | ELECTRIC - UNDERGROUND | LHANLY | Approved | |
05/29/2013 | ELECTRIC - UFER | LHANLY | Approved | |
05/29/2013 | SHEET ROCK NAILING | LHANLY | Approved | |
07/03/2013 | TEP CLEARANCE - AM | LHANLY | Approved | 1303-1306 1403-1406 1509-1523 1609-1623 1709-1723 |
07/08/2013 | MECHANICAL - ABOVE CEILING | LHANLY | Approved | |
07/08/2013 | ELECTRIC - TEMPORARY SERVICE | LHANLY | Approved | |
07/08/2013 | ELECTRIC - CABLE DROP | LHANLY | Approved | |
07/19/2013 | PLUMBING - GAS PRESS TEST FNL | LHANLY | Approved | |
07/19/2013 | PLUMBING - GAS PRESSURE TEST | LHANLY | Approved | |
07/19/2013 | PLUMBING - GAS PRESS TEST FNL | LHANLY | Approved | |
07/19/2013 | PLUMBING - GAS PRESSURE TEST | LHANLY | Approved | |
07/19/2013 | ELECTRIC - PROGRESS | LHANLY | Approved | |
07/19/2013 | ELECTRIC - ABOVE CEILING | LHANLY | Approved | |
07/19/2013 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
07/19/2013 | ELECTRIC - ABOVE CEILING | LHANLY | Approved | |
07/19/2013 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
07/23/2013 | FIRE - ALARM FINAL | CBASALDU | Approved | |
07/30/2013 | FIRE SPKLR - FINAL | CBASALDU | Approved | |
07/30/2013 | FIRE SPKLR - OH PIPING & HYDRO | CBASALDU | Approved | |
08/14/2013 | FIREWALL/FIREBARRIER/FIRESTOP | LHANLY | Approved | |
08/14/2013 | PLUMBING - FINAL | LHANLY | Approved | |
08/14/2013 | MECHANICAL - FINAL | LHANLY | Approved | |
08/14/2013 | BUILDING - PROGRESS | LHANLY | Approved | |
08/14/2013 | BUILDING - PROGRESS | LHANLY | Approved | |
08/14/2013 | FIREWALL/FIREBARRIER/FIRESTOP | LHANLY | Approved | FIRESTOP IN ELECTRIC ROOMS INCOMPLETE |
08/16/2013 | FIRE - FINAL | CBASALDU | Approved | |
11/19/2013 | ELECTRIC - FINAL | JMANCHESTER | Approved | |
11/19/2013 | BUILDING - FINAL | LHANLY | Approved |