Permit Details

Status:
C of o
Type:
MULTI FAMILY NEW
Address NEW:
350 E CONGRESS ST
Apply Date:
04/19/2012
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
STUDENT HOUSING
Contractors:
  • SUMMIT BUILDERS ,

Permit Reviews

Permit Number - T12CM02061
Permit Status: C of o
Permit Description: STUDENT HOUSING
Start Date Submittal Complete Date Status  
04/19/2012 PLANS OK TO SUBMIT - COMM 04/19/2012 COMPLETED Review Details
04/19/2012 COMMERCIAL - NEW 07/03/2012 COMPLETED Review Details
06/07/2013 REVISION - - 1ST 06/12/2013 COMPLETED Review Details
06/12/2013 REVISION - - 1ST 06/21/2013 COMPLETED Review Details
06/21/2013 REVISION - - 1ST 06/21/2013 COMPLETED Review Details
07/03/2012 RESUBMITTAL 08/09/2012 COMPLETED Review Details
08/09/2012 RESUBMITTAL 11/05/2012 COMPLETED Review Details
11/05/2012 RESUBMITTAL 11/05/2012 COMPLETED Review Details

Completed Inspections

Permit Status: C of o
Permit Number: T12CM02061
Permit Description: STUDENT HOUSING
Total Completed Inspections - 44
Date Description Inspector Results Comments
10/25/2012 BUILDING PRE-SLAB LHANLY Approved DECK POURS 1 & 2 APPROVED
05/16/2013 PLUMBING - SEWER HCS CONNECT LHANLY Approved
05/16/2013 PLUMBING - GAS PRESSURE TEST LHANLY Approved
05/17/2013 PLUMBING - PRE SLAB LHANLY Approved
05/17/2013 PLUMBING - ROUGH, SOIL LHANLY Approved
05/17/2013 U VALUE FOR WINDOW LHANLY Approved
05/17/2013 STUCCO MESH LHANLY Approved
05/17/2013 ROOF NAILING LHANLY Approved
05/17/2013 EXT METAL CLIPS/EXT SHEATHING LHANLY Approved
05/17/2013 REINFORCED MASONRY PRE-GROUT LHANLY Approved
05/29/2013 PLUMBING - INTERMEDIATE LHANLY Approved
05/29/2013 PLUMBING - YARD WTR LINE/TEST LHANLY Approved
05/29/2013 PLUMBING - ABOVE CEILING LHANLY Approved
05/29/2013 PLUMBING - INTERMEDIATE LHANLY Approved LEVEL 1 - 6 EXCEPT NORTH END
07/05/2013 TEP CLEARANCE - AM LHANLY Approved ECO 2102,2103,
2210-2219,2301-2319,2401-2419,2501-2519, 2601-2619
07/05/2013 PLUMBING - ROOF DRAINS LHANLY Approved
07/05/2013 MECHANICAL - INTERMEDIATE LHANLY Approved
07/05/2013 FRAMING LHANLY Approved
07/05/2013 ELECTRIC - TEMP POWER FOR TEST LHANLY Approved
07/05/2013 ELECTRIC - ABOVE CEILING LHANLY Approved
07/05/2013 ELECTRIC - INTERMEDIATE LHANLY Approved
07/19/2013 PLUMBING - PROGRESS LHANLY Approved
07/19/2013 MECHANICAL - ABOVE CEILING LHANLY Approved
07/19/2013 SHEET ROCK NAILING LHANLY Approved
07/19/2013 ELECTRIC - PROGRESS LHANLY Approved
07/19/2013 ELECTRIC - OUTDOOR LIGHTING LHANLY Approved
07/30/2013 FIRE SPKLR - OH PIPING & HYDRO CBASALDU Approved
07/30/2013 FIRE SPKLR - UG PIPING FLUSH CBASALDU Approved
07/30/2013 FIRE SPKLR - UG, PIPING, HYDRO CBASALDU Approved
08/29/2013 PLUMBING - FINAL LHANLY Approved
08/29/2013 PLUMBING - GAS PRESS TEST FNL LHANLY Approved
08/29/2013 MECHANICAL - FINAL LHANLY Approved
08/29/2013 BUILDING - PROGRESS LHANLY Approved
08/29/2013 FIREWALL/FIREBARRIER/FIRESTOP LHANLY Approved
08/29/2013 BUILDING ABOVE CEILING LHANLY Approved
09/26/2013 FIRE - LANE SIGNS KENB Approved
09/26/2013 FIRE - HYDRANTS KENB Approved
09/26/2013 FIRE - ALARM FINAL KENB Approved
11/14/2013 FIRE - FINAL wmotto Approved
11/14/2013 FIRE SPKLR - FINAL wmotto Approved
11/19/2013 BUILDING - FINAL LHANLY Approved
11/19/2013 ELECTRIC - FINAL LHANLY Approved
11/19/2013 ELECTRIC - FINAL LHANLY Approved
11/19/2013 BUILDING - FINAL LHANLY Approved WAITING ON FINAL SELECTIVE COORDINATION REPORT AND VERIFICATION