Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T12CM02061
Permit Details
Apply Date:
04/19/2012
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
STUDENT HOUSING
Contractors:
- SUMMIT BUILDERS ,
Permit Reviews
Permit Number - T12CM02061
Permit Status: C of o
Permit Description: STUDENT HOUSING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/19/2012 | PLANS OK TO SUBMIT - COMM | 04/19/2012 | COMPLETED |
04/19/2012 | COMMERCIAL - NEW | 07/03/2012 | COMPLETED |
06/07/2013 | REVISION - - 1ST | 06/12/2013 | COMPLETED |
06/12/2013 | REVISION - - 1ST | 06/21/2013 | COMPLETED |
06/21/2013 | REVISION - - 1ST | 06/21/2013 | COMPLETED |
07/03/2012 | RESUBMITTAL | 08/09/2012 | COMPLETED |
08/09/2012 | RESUBMITTAL | 11/05/2012 | COMPLETED |
11/05/2012 | RESUBMITTAL | 11/05/2012 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM02061
Permit Description: STUDENT HOUSING
Total Completed Inspections - 44
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/25/2012 | BUILDING PRE-SLAB | LHANLY | Approved | DECK POURS 1 & 2 APPROVED |
05/16/2013 | PLUMBING - SEWER HCS CONNECT | LHANLY | Approved | |
05/16/2013 | PLUMBING - GAS PRESSURE TEST | LHANLY | Approved | |
05/17/2013 | PLUMBING - PRE SLAB | LHANLY | Approved | |
05/17/2013 | PLUMBING - ROUGH, SOIL | LHANLY | Approved | |
05/17/2013 | U VALUE FOR WINDOW | LHANLY | Approved | |
05/17/2013 | STUCCO MESH | LHANLY | Approved | |
05/17/2013 | ROOF NAILING | LHANLY | Approved | |
05/17/2013 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | |
05/17/2013 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | |
05/29/2013 | PLUMBING - INTERMEDIATE | LHANLY | Approved | |
05/29/2013 | PLUMBING - YARD WTR LINE/TEST | LHANLY | Approved | |
05/29/2013 | PLUMBING - ABOVE CEILING | LHANLY | Approved | |
05/29/2013 | PLUMBING - INTERMEDIATE | LHANLY | Approved | LEVEL 1 - 6 EXCEPT NORTH END |
07/05/2013 | TEP CLEARANCE - AM | LHANLY | Approved | ECO 2102,2103, 2210-2219,2301-2319,2401-2419,2501-2519, 2601-2619 |
07/05/2013 | PLUMBING - ROOF DRAINS | LHANLY | Approved | |
07/05/2013 | MECHANICAL - INTERMEDIATE | LHANLY | Approved | |
07/05/2013 | FRAMING | LHANLY | Approved | |
07/05/2013 | ELECTRIC - TEMP POWER FOR TEST | LHANLY | Approved | |
07/05/2013 | ELECTRIC - ABOVE CEILING | LHANLY | Approved | |
07/05/2013 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
07/19/2013 | PLUMBING - PROGRESS | LHANLY | Approved | |
07/19/2013 | MECHANICAL - ABOVE CEILING | LHANLY | Approved | |
07/19/2013 | SHEET ROCK NAILING | LHANLY | Approved | |
07/19/2013 | ELECTRIC - PROGRESS | LHANLY | Approved | |
07/19/2013 | ELECTRIC - OUTDOOR LIGHTING | LHANLY | Approved | |
07/30/2013 | FIRE SPKLR - OH PIPING & HYDRO | CBASALDU | Approved | |
07/30/2013 | FIRE SPKLR - UG PIPING FLUSH | CBASALDU | Approved | |
07/30/2013 | FIRE SPKLR - UG, PIPING, HYDRO | CBASALDU | Approved | |
08/29/2013 | PLUMBING - FINAL | LHANLY | Approved | |
08/29/2013 | PLUMBING - GAS PRESS TEST FNL | LHANLY | Approved | |
08/29/2013 | MECHANICAL - FINAL | LHANLY | Approved | |
08/29/2013 | BUILDING - PROGRESS | LHANLY | Approved | |
08/29/2013 | FIREWALL/FIREBARRIER/FIRESTOP | LHANLY | Approved | |
08/29/2013 | BUILDING ABOVE CEILING | LHANLY | Approved | |
09/26/2013 | FIRE - LANE SIGNS | KENB | Approved | |
09/26/2013 | FIRE - HYDRANTS | KENB | Approved | |
09/26/2013 | FIRE - ALARM FINAL | KENB | Approved | |
11/14/2013 | FIRE - FINAL | wmotto | Approved | |
11/14/2013 | FIRE SPKLR - FINAL | wmotto | Approved | |
11/19/2013 | BUILDING - FINAL | LHANLY | Approved | |
11/19/2013 | ELECTRIC - FINAL | LHANLY | Approved | |
11/19/2013 | ELECTRIC - FINAL | LHANLY | Approved | |
11/19/2013 | BUILDING - FINAL | LHANLY | Approved | WAITING ON FINAL SELECTIVE COORDINATION REPORT AND VERIFICATION |