Permit: T12CM01324
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
2930 N SWAN RD #209
Address NEW:
2930 N SWAN RD #209
Apply Date:
03/23/2012
Applicant:
LANCE, GEORGE GERARD
Description:
TI: OFFICE
Architects:
- LANCE, GEORGE GERARD
Contractors:
- BARKER MORRISSEY CONTRACTING INC **APA**
Permit Reviews
Permit Number - T12CM01324
Permit Status: C of o
Permit Description: TI: OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/23/2012 | COMMERCIAL - TI | 04/23/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM01324
Permit Status: C of o
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/23/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM01324
Permit Description: TI: OFFICE
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/16/2012 | PLUMBING - ROUGH, SOIL | JMILITEL | Approved | IVRS - Inspection :* |
| 05/22/2012 | PLUMBING - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 05/22/2012 | ELECTRIC - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 05/22/2012 | FRAMING | JMILITEL | Approved | IVRS - Inspection :* |
| 06/01/2012 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 06/29/2012 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 06/29/2012 | PLUMBING - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 06/29/2012 | ELECTRIC - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 06/29/2012 | BUILDING ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 07/13/2012 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
| 07/16/2012 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 07/16/2012 | PLUMBING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 07/16/2012 | PLUMBING - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 07/16/2012 | ELECTRIC - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 07/16/2012 | ELECTRIC - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 07/16/2012 | BUILDING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 07/16/2012 | NPPO - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
| 07/16/2012 | SIGN - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
| 07/16/2012 | LANDSCAPE - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
| 07/16/2012 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 07/17/2012 | SHEET ROCK NAILING | JMILITEL | Approved | |
| 07/17/2012 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | |
| 07/17/2012 | FIRE - FINAL | CSCHULTZ | Approved |