Permit: T12CM00542
Permit Details
Apply Date:
02/21/2012
Applicant:
PECORD, PHILLIP C
Description:
NEW RETAIL AUTO ZONE STORE
Architects:
- PECORD, PHILLIP C
Contractors:
- VAN TASSEL PROCTOR INC
Permit Reviews
Permit Number - T12CM00542
Permit Status: C of o
Permit Description: NEW RETAIL AUTO ZONE STORE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/21/2012 | PLANS OK TO SUBMIT - COMM | 02/21/2012 | COMPLETED |
| 02/21/2012 | COMMERCIAL - NEW | 03/21/2012 | COMPLETED |
| 05/04/2012 | RESUBMITTAL | 06/04/2012 | COMPLETED |
| 06/26/2012 | RESUBMITTAL | 07/23/2012 | COMPLETED |
| 07/23/2012 | RESUBMITTAL | 07/23/2012 | COMPLETED |
| 07/23/2012 | RESUBMITTAL | 08/22/2012 | COMPLETED |
| 08/22/2012 | RESUBMITTAL | 08/30/2012 | COMPLETED |
| 08/30/2012 | RESUBMITTAL | 09/05/2012 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM00542
Permit Description: NEW RETAIL AUTO ZONE STORE
Total Completed Inspections - 38
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/03/2012 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | -1ST LIFT (GROUT) -RECEIVED SPECIAL INSP. REPORTS FOR CONCRETE AND REBAR. |
| 10/03/2012 | ELECTRIC - UFER | RCAMACHO | Approved | IVRS - Inspection :* |
| 10/08/2012 | PLUMBING - PRE SLAB | DSANTACR | Approved | IVRS - Inspection :* |
| 10/11/2012 | BUILDING PRE-SLAB | RCAMACHO | Approved | IVRS - Inspection :* |
| 10/30/2012 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | IVRS - Inspection :* |
| 11/02/2012 | REINFORCED MASONRY PRE-GROUT | DSANTACR | Approved | IVRS - Inspection :* |
| 11/05/2012 | PLUMBING - SEWER HCS CONNECT | DSANTACR | Approved | IVRS - Inspection :* |
| 11/08/2012 | PLUMBING - YARD WTR LINE/TEST | RCAMACHO | Approved | IVRS - Inspection :* |
| 11/14/2012 | PLUMBING - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 11/14/2012 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 11/14/2012 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | IVRS - Inspection :* |
| 11/14/2012 | FRAMING | RCAMACHO | Approved | IVRS - Inspection :* |
| 11/19/2012 | SHEET ROCK NAILING | MRAMBER | Approved | IVRS - Inspection :* |
| 12/10/2012 | BUILDING - PROGRESS | RLEDONNE | Approved | THIS INSPECTION FOR THE SIGN NOT BUILDING THE SIGN HAS AN OTHER ACTIVITY AND PERMIT. |
| 12/11/2012 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* |
| 12/12/2012 | TEP CLEARANCE - AM | DSANTACR | Approved | OK TO CLEAR TEC |
| 12/28/2012 | MECHANICAL - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 12/28/2012 | PLUMBING - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 12/28/2012 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 12/28/2012 | BUILDING - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 12/31/2012 | MECHANICAL - ABOVE CEILING | DSANTACR | Approved | OK PER MECHANICAL FINAL BY DSANTACRUZ |
| 12/31/2012 | MECHANICAL - INTERMEDIATE | DSANTACR | Approved | OK PER MECHANICAL FINAL BY DSANTACRUZ |
| 12/31/2012 | PLUMBING - PROGRESS | DSANTACR | Approved | OK PER PLUMBING FINAL BY DSANTACRUZ |
| 12/31/2012 | PLUMBING - ABOVE CEILING | DSANTACR | Approved | OK PER PLUMBING FINAL BY DSANTACRUZ |
| 12/31/2012 | PLUMBING - ROUGH, SOIL | DSANTACR | Approved | OK PER PLUMBING FINAL BY DSANTACRUZ |
| 12/31/2012 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | OK PER ELECTRIC FINAL BY DSANTACRUZ |
| 12/31/2012 | ELECTRIC - PROGRESS | DSANTACR | Approved | OK PER ELECTRIC FINAL BY DSANTACRUZ |
| 12/31/2012 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | OK PER ELECTRIC FINAL BY DSANTACRUZ |
| 12/31/2012 | FIREWALL/FIREBARRIER/FIRESTOP | DSANTACR | Approved | OK PER BUILDING FINAL BY DSANTACRUZ |
| 12/31/2012 | U VALUE FOR WINDOW | DSANTACR | Approved | OK PER BUILDING FINAL BY DSANTACRUZ |
| 12/31/2012 | STUCCO MESH | DSANTACR | Approved | OK PER BUILDING FINAL BY DSANTACRUZ |
| 12/31/2012 | BUILDING ABOVE CEILING | DSANTACR | Approved | OK PER BUILDING FINAL BY DSANTACRUZ |
| 12/31/2012 | FIRE - FINAL | CSCHULTZ | Approved | |
| 01/03/2013 | NPPO - FINAL | RLEDONNE | Approved | |
| 01/03/2013 | SIGN - FINAL | RLEDONNE | Approved | |
| 01/03/2013 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 01/03/2013 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 01/09/2013 | RIGHT OF WAY - FINAL | MCASTRO | Approved |