Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
1401 S ALVERNON WY
Apply Date:
12/13/2011
Applicant:
MIKE WOOTEN
Description:
NEW CONVENIENCE STORE-QUIK TRIP @ ALVERNON
Architects:
  • FILUK, DANIEL DIMITRI
Contractors:
  • M T V GENERAL CONTRACTORS INC ,

Permit Reviews

Permit Number - T11CM03806
Permit Status: C of o
Permit Description: NEW CONVENIENCE STORE-QUIK TRIP @ ALVERNON
Start Date Submittal Complete Date Status  
03/13/2012 RESUBMITTAL 04/02/2012 COMPLETED Review Details
04/02/2012 RESUBMITTAL 04/02/2012 COMPLETED Review Details
04/02/2012 RESUBMITTAL 04/13/2012 COMPLETED Review Details
12/13/2011 PLANS OK TO SUBMIT - COMM 12/13/2011 COMPLETED Review Details
12/13/2011 COMMERCIAL - NEW 02/24/2012 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T11CM03806
Permit Status: C of o
Permit Description: NEW CONVENIENCE STORE-QUIK TRIP @ ALVERNON
Total Outstanding Activity Conditions - 1
Date Name
12/13/2011 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T11CM03806
Permit Description: NEW CONVENIENCE STORE-QUIK TRIP @ ALVERNON
Total Completed Inspections - 43
Date Description Inspector Results Comments
05/30/2012 STEM WALL/RETAINING WALL JBURGE Approved IVRS - Inspection :*
06/01/2012 PLUMBING - SEWER HCS CONNECT JBURGE Approved IVRS - Inspection :*
06/05/2012 SITE - SEWER JBURGE Approved IVRS - Inspection :*
06/05/2012 PLUMBING - ROUGH, SOIL JBURGE Approved IVRS - Inspection :*
06/05/2012 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved IVRS - Inspection :*
06/07/2012 ELECTRIC - UNDERGROUND JBURGE Approved IVRS - Inspection :*
06/07/2012 PLUMBING - PRE SLAB JBURGE Approved IVRS - Inspection :*
06/07/2012 BUILDING PRE-SLAB JBURGE Approved IVRS - Inspection :*
06/13/2012 PLUMBING - YARD WTR LINE/TEST JBURGE Approved IVRS - Inspection :*
07/10/2012 REINFORCED MASONRY PRE-GROUT JBURGE Approved IVRS - Inspection :*
07/13/2012 PLUMBING - ROOF DRAINS JBURGE Approved IVRS - Inspection :*
07/19/2012 ROOF NAILING JBURGE Approved IVRS - Inspection :*(PARAPET SHEATHING) - OK TO DRY-IN & COVER
07/19/2012 PLUMBING - INTERMEDIATE JBURGE Approved IVRS - Inspection :*
08/02/2012 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
08/02/2012 FRAMING JBURGE Approved IVRS - Inspection :*
08/10/2012 TEP CLEARANCE - AM JBURGE Approved OK TO ENERGIZE CODE ECO
08/20/2012 MECHANICAL - ABOVE CEILING JBURGE Approved IVRS - Inspection :*
08/20/2012 PLUMBING - ABOVE CEILING JBURGE Approved IVRS - Inspection :*
08/20/2012 ELECTRIC - ABOVE CEILING JBURGE Approved IVRS - Inspection :*
08/20/2012 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
09/10/2012 MECHANICAL - FINAL JBURGE Approved IVRS - Inspection :*
09/10/2012 PLUMBING - PROGRESS JBURGE Approved IVRS - Inspection :*
09/10/2012 PLUMBING - FINAL JBURGE Approved IVRS - Inspection :*
09/13/2012 MECHANICAL - INTERMEDIATE JBURGE Approved IVRS - Inspection :*
09/17/2012 ELECTRIC - PROGRESS RMORENO Approved IVRS - Inspection :*
09/17/2012 ELECTRIC - INTERMEDIATE RMORENO Approved IVRS - Inspection :*
09/17/2012 ELECTRIC - UFER RMORENO Approved IVRS - Inspection :*
09/17/2012 ELECTRIC - FINAL RMORENO Approved IVRS - Inspection :*
09/17/2012 ELECTRIC - OUTDOOR LIGHTING RMORENO Approved IVRS - Inspection :*
09/19/2012 RIGHT OF WAY - FINAL T.Savoca Approved
09/20/2012 FIRE - FINAL CFUNKE Approved
09/20/2012 NPPO - FINAL MRUSSO Approved
09/20/2012 SIGN - FINAL MRUSSO Approved
09/20/2012 LANDSCAPE - FINAL MRUSSO Approved
09/20/2012 ENGINEERING - FINAL MRUSSO Approved
09/21/2012 OUTDOOR LIGHTING FINAL JBURGE Approved PER FINAL
09/21/2012 BUILDING - PROGRESS JBURGE Approved PER BUILDING FINAL
09/21/2012 U VALUE FOR WINDOW JBURGE Approved per building final
09/21/2012 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
09/21/2012 STUCCO MESH JBURGE Approved IVRS - Inspection :*
09/21/2012 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved IVRS - Inspection :*
09/24/2012 ELECTRIC - TEMPORARY SERVICE JBURGE Approved PER FINAL
01/15/2013 HEALTH DEPT - FINAL 724-7908 NRAMIREZ Approved