Permit: T11CM03331
Permit Details
Apply Date:
10/20/2011
Applicant:
KATZ, LEO ROBERT
Description:
ADD DETACHED SLEEPING QUARTERS W/BATH & GARAGE, REMODEL EXISTING SFR; ~60 LF Masonry Wall < 6'; ~150 LF Metal Fence < 6'
Architects:
- KATZ, LEO ROBERT
Permit Reviews
Permit Number - T11CM03331
Permit Status: C of o
Permit Description: ADD DETACHED SLEEPING QUARTERS W/BATH & GARAGE, REMODEL EXISTING SFR; ~60 LF Masonry Wall < 6'; ~150 LF Metal Fence < 6'
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/20/2011 | RESIDENTIAL - BLDG/ZONING/ENGINE/WWM | 10/20/2011 | COMPLETED |
10/20/2011 | RESIDENTIAL - BLDG/WWM | 11/10/2011 | COMPLETED |
11/10/2011 | RESUBMITTAL | 11/16/2011 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM03331
Permit Description: ADD DETACHED SLEEPING QUARTERS W/BATH & GARAGE, REMODEL EXISTING SFR; ~60 LF Masonry Wall < 6'; ~150 LF Metal Fence < 6'
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/17/2011 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | IVRS - Inspection :* |
11/17/2011 | ELECTRIC - UFER | DQUINN | Approved | IVRS - Inspection :* |
11/17/2011 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
11/18/2011 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | IVRS - Inspection :* |
12/09/2011 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | IVRS - Inspection :* |
12/28/2011 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* |
12/30/2011 | PLUMBING - INTERMEDIATE | DQUINN | Approved | 1) ROUGH PLUMB IN FRONT HOUSE OK TO COVER |
01/06/2012 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
01/06/2012 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | IVRS - Inspection :* |
01/23/2012 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER L. HANLY |
01/23/2012 | ELECTRIC - SERVICE UPGRADE | LHANLY | Approved | OK TO CLEAR TEC ONLY. STILL NEED TO SEE UNDERGROUND AND SWAP-OVER TO MAIN HOUSE. |
01/27/2012 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | IVRS - Inspection :* |
01/27/2012 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
01/27/2012 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
01/30/2012 | STUCCO MESH | DQUINN | Approved | IVRS - Inspection :* |
02/14/2012 | ELECTRIC - UNDERGROUND | DQUINN | Approved | IVRS - Inspection :* |
02/14/2012 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
02/21/2012 | FRAMING | DQUINN | Approved | |
03/23/2012 | U VALUE FOR WINDOW | LHANLY | Approved | |
09/17/2012 | BUILDING - PROGRESS | LHANLY | Approved | |
09/17/2012 | MECHANICAL - PROGRESS | LHANLY | Approved | |
09/17/2012 | PLUMBING - PROGRESS | LHANLY | Approved | |
09/17/2012 | ELECTRIC - PROGRESS | LHANLY | Approved | |
09/17/2012 | MECHANICAL - FINAL | LHANLY | Approved | |
09/17/2012 | PLUMBING - FINAL | LHANLY | Approved | |
09/17/2012 | OUTDOOR LIGHTING FINAL | LHANLY | Approved | |
09/17/2012 | ELECTRIC - FINAL | LHANLY | Approved | |
09/17/2012 | BUILDING - FINAL | LHANLY | Approved |